Agenda/Minutes of the VIS Meeting on 2020/7/31

2020/7/31 14:00 -

Zoom Meeting

Participants:

Progress report

General

Type-A

  • The accelerometer with LVDT was tested at the site (report).

Type-B

Type-Bp

Type-C

Controls

Electronics

Towards O4

  • KAGRA is in "Upgrade phase for O4". Upgrade of SR controls were performed. The accelerometer with LVDT was tested at the site.
  • Plan for cleaning the clean booth (EN, JP) will be submitted by 3rd. Aug. It is necessary to make the inventory with location (example for Type-A).

  • Preparation work (pre-cleaning) will be started from 17th Sep. Cleaning schedule.png.

cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List), Schedule towards O4 (Chart).

Safety

Discussion

  • [Washimi] PEM team introduce the Holobuilder (Google street view like tool). Let's discuss about cleanup plan with this tool.

Travel Plans

Next meeting

  • On 2020/8/7(Fri)