Line 30: Line 30:
 * Brainstorming meeting for IMMT2 modification was held yesterday. We discussed the modified shape of the outer frame and how to replace it. The plan is to replace the frame without removing IMMT2 from the chamber.
Line 47: Line 49:
  * [Washimi] Room Temmperature report([[https://www.icrr.u-tokyo.ac.jp/~washimi/KAGRA/SEM/fig_GAS/]])
    * We turned on the FFUs in CS and Y-end on 2020-8-3 to recover the room temperature ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14851|klog14851]]) ->RT becames about the same as before the heavy rain.
    * BS temperature was droped (~0.6 degC) in this morning ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14879|klog14879]]) -> The Ondotori was dropped.

Agenda/Minutes of the VIS Meeting on 2020/8/7

2020/8/7 14:00 -

Zoom Meeting

Participants:

Progress report

General

Type-A

  • [Miyo] Installed the Prequa system in TypeA

    • (This week) Installation was finished. Now I try to diagonalize sensors and balance actuators by using the Prequa system.
    • (Next week) I will do the modal damping on TypeA suspensions after the initialization work for sensors and actuators.

Type-B

  • On Monday I submitted the paper to CPC: JGW-P2011860.

  • Noise budget paper: I calculated upper limits to DAC and coil driver noise contribution to DARM for the BS: klog 14875.

Type-Bp

  • Noise budget paper: Fabian calculated upper limits to DAC and coil driver noise contribution to DARM for PRM: klog 14876.

Type-C

  • Brainstorming meeting for IMMT2 modification was held yesterday. We discussed the modified shape of the outer frame and how to replace it. The plan is to replace the frame without removing IMMT2 from the chamber.

Controls

Electronics

Towards O4

  • KAGRA is in "Upgrade phase for O4". PreQua system was implemented to the Type-A.

  • Confirmation of personnel at the site.
    • Type-A team: Takahashi, Sato, Miyo, + Company(Jan-Apr)
    • Type-B/Bp team: (Shoda,) Hirata, Fabian, Washimi, + Company(Oct-Dec)
  • Procedure documents are required by SEO.
  • Schedule towards O4 (Chart) was revised.

cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List).

Safety

Discussion

Travel Plans

Next meeting

  • On 2020/8/19(Wed)?

KAGRA/Subgroups/VIS/VISMinutes20200807 (last edited 2020-08-07 14:58:03 by RyutaroTakahashi)