Agenda/Minutes of the VIS Meeting on 2020/8/7
2020/8/7 14:00 -
Participants:
Progress report
General
[Miyo] by 08/28/2020?, 20% done (+0%), Make a cabling diagram for O4
[Miyo] by 08/28/2020?, 25% done (+0%), Make prototype system for temperature control
[Miyo] by 08/28/2020?, 20% done (+0%), Enable to control the limit switch of stepper motor
[Miyo] by 08/28/2020?, 0% done (+0%), Request AEL chassis for picomotor driver
[Miyo] by 08/28/2020?, 0% done (+0%), Update remote control system
[Miyo] by 08/28/2020?, 0% done (+0%), Add CRY stepper motor in the remote control system
Type-A
[Miyo] Installed the Prequa system in TypeA
- (This week) Installation was finished. Now I try to diagonalize sensors and balance actuators by using the Prequa system.
- (Next week) I will do the modal damping on TypeA suspensions after the initialization work for sensors and actuators.
Type-B
On Monday I submitted the paper to CPC: JGW-P2011860.
Noise budget paper: I calculated upper limits to DAC and coil driver noise contribution to DARM for the BS: klog 14875.
Type-Bp
Noise budget paper: Fabian calculated upper limits to DAC and coil driver noise contribution to DARM for PRM: klog 14876.
Type-C
- Brainstorming meeting for IMMT2 modification was held yesterday. We discussed the modified shape of the outer frame and how to replace it. The plan is to replace the frame without removing IMMT2 from the chamber.
Controls
Electronics
Towards O4
KAGRA is in "Upgrade phase for O4". PreQua system was implemented to the Type-A.
- Confirmation of personnel at the site.
- Type-A team: Takahashi, Sato, Miyo, + Company(Jan-Apr)
- Type-B/Bp team: (Shoda,) Hirata, Fabian, Washimi, + Company(Oct-Dec)
- Procedure documents are required by SEO.
- Wire gluing in PR3 (by Shoda)
- Filter height adjustment in Type-B (by Fabian)
Schedule towards O4 (Chart) was revised.
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List).
Safety
[Washimi] Room Temmperature report(https://www.icrr.u-tokyo.ac.jp/~washimi/KAGRA/SEM/fig_GAS/)
Discussion
Travel Plans
Next meeting
- On 2020/8/19(Wed)?