Differences between revisions 8 and 10 (spanning 2 versions)
Revision 8 as of 2020-08-07 09:11:16
Size: 2054
Comment:
Revision 10 as of 2020-08-07 13:25:49
Size: 2879
Editor: KousekiMiyo
Comment:
Deletions are marked like this. Additions are marked like this.
Line 10: Line 10:
 * [Miyo] by 08/28/2020?, 20% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/13|Make a cabling diagram for O4]]
 * [Miyo] by 08/28/2020?, 25% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/20|Make prototype system for temperature control]]
 * [Miyo] by 08/28/2020?, 20% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/22|Enable to control the limit switch of stepper motor]]
 * [Miyo] by 08/28/2020?, 0% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/23|Request AEL chassis for picomotor driver]]
 * [Miyo] by 08/28/2020?, 0% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/24|Update remote control system]]
 * [Miyo] by 08/28/2020?, 0% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/25|Add CRY stepper motor in the remote control system]]
Line 31: Line 38:
 * Schedule towards O4 ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Chart]]) was revised.
Line 32: Line 40:
cf. Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]), Task towards O4 ([[https://www.dropbox.com/s/60oygtwmckmdyj6/Towards%20O4%20on%20VIS%20.xlsx?dl=0|List]]), Schedule towards O4 ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Chart]]). cf. Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]), Task towards O4 ([[https://www.dropbox.com/s/60oygtwmckmdyj6/Towards%20O4%20on%20VIS%20.xlsx?dl=0|List]]).

Agenda/Minutes of the VIS Meeting on 2020/8/7

2020/8/7 14:00 -

Zoom Meeting

Participants:

Progress report

General

Type-A

Type-B

  • On Monday I submitted the paper to CPC: JGW-P2011860.

  • Noise budget paper: I calculated upper limits to DAC and coil driver noise contribution to DARM for the BS: klog 14875.

Type-Bp

  • Noise budget paper: Fabian calculated upper limits to DAC and coil driver noise contribution to DARM for PRM: klog 14876.

Type-C

Controls

Electronics

Towards O4

  • KAGRA is in "Upgrade phase for O4". PreQua system was implemented to the Type-A.

  • Confirmation of personnel at the site.
    • Type-A team: Takahashi, Sato, Miyo, + Company(Jan-Apr)
    • Type-B/Bp team: (Shoda,) Hirata, Fabian, Washimi, + Company(Oct-Dec)
  • Procedure documents are required by SEO.
  • Schedule towards O4 (Chart) was revised.

cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List).

Safety

Discussion

Travel Plans

Next meeting

  • On 2020/8/19(Wed)?

KAGRA/Subgroups/VIS/VISMinutes20200807 (last edited 2020-08-07 14:58:03 by RyutaroTakahashi)