cf. Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]), Task towards O4 ([[https://www.dropbox.com/s/60oygtwmckmdyj6/Towards%20O4%20on%20VIS%20.xlsx?dl=0|List]]), Schedule towards O4 ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Chart]]). | cf. Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]), Task towards O4 ([[https://www.dropbox.com/s/60oygtwmckmdyj6/Towards%20O4%20on%20VIS%20.xlsx?dl=0|List]]). |
Agenda/Minutes of the VIS Meeting on 2020/8/7
2020/8/7 14:00 -
Participants:
Progress report
General
Type-A
Type-B
On Monday I submitted the paper to CPC: JGW-P2011860.
Noise budget paper: I calculated upper limits to DAC and coil driver noise contribution to DARM for the BS: klog 14875.
Type-Bp
Noise budget paper: Fabian calculated upper limits to DAC and coil driver noise contribution to DARM for PRM: klog 14876.
Type-C
Controls
Electronics
Towards O4
KAGRA is in "Upgrade phase for O4". PreQua system was implemented to the Type-A.
- Confirmation of personnel at the site.
- Type-A team: Takahashi, Sato, Miyo, + Company(Jan-Apr)
- Type-B/Bp team: (Shoda,) Hirata, Fabian, Washimi, + Company(Oct-Dec)
- Procedure documents are required by SEO.
- Wire gluing in PR3 (by Shoda)
- Filter height adjustment in Type-B (by Fabian)
Schedule towards O4 (Chart) was revised.
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List).
Safety
Discussion
Travel Plans
Next meeting
- On 2020/8/19(Wed)?