* [Miyo] by 08/28/2020?, 20% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/13|Make a cabling diagram for O4]] * [Miyo] by 08/28/2020?, 25% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/20|Make prototype system for temperature control]] * [Miyo] by 08/28/2020?, 20% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/22|Enable to control the limit switch of stepper motor]] * [Miyo] by 08/28/2020?, 0% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/23|Request AEL chassis for picomotor driver]] * [Miyo] by 08/28/2020?, 0% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/24|Update remote control system]] * [Miyo] by 08/28/2020?, 0% done (+0%), [[https://github.com/gw-vis/kagra-vis/issues/25|Add CRY stepper motor in the remote control system]] |
|
Line 11: | Line 18: |
* [Miyo] [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14861|Installed the Prequa system in TypeA]] |
Agenda/Minutes of the VIS Meeting on 2020/8/7
2020/8/7 14:00 -
Participants:
Progress report
General
[Miyo] by 08/28/2020?, 20% done (+0%), Make a cabling diagram for O4
[Miyo] by 08/28/2020?, 25% done (+0%), Make prototype system for temperature control
[Miyo] by 08/28/2020?, 20% done (+0%), Enable to control the limit switch of stepper motor
[Miyo] by 08/28/2020?, 0% done (+0%), Request AEL chassis for picomotor driver
[Miyo] by 08/28/2020?, 0% done (+0%), Update remote control system
[Miyo] by 08/28/2020?, 0% done (+0%), Add CRY stepper motor in the remote control system
Type-A
Type-B
On Monday I submitted the paper to CPC: JGW-P2011860.
Noise budget paper: I calculated upper limits to DAC and coil driver noise contribution to DARM for the BS: klog 14875.
Type-Bp
Noise budget paper: Fabian calculated upper limits to DAC and coil driver noise contribution to DARM for PRM: klog 14876.
Type-C
Controls
Electronics
Towards O4
KAGRA is in "Upgrade phase for O4". PreQua system was implemented to the Type-A.
- Confirmation of personnel at the site.
- Type-A team: Takahashi, Sato, Miyo, + Company(Jan-Apr)
- Type-B/Bp team: (Shoda,) Hirata, Fabian, Washimi, + Company(Oct-Dec)
- Procedure documents are required by SEO.
- Wire gluing in PR3 (by Shoda)
- Filter height adjustment in Type-B (by Fabian)
Schedule towards O4 (Chart) was revised.
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List).
Safety
Discussion
Travel Plans
Next meeting
- On 2020/8/19(Wed)?