Differences between revisions 1 and 10 (spanning 9 versions)
Revision 1 as of 2020-08-27 09:26:42
Size: 1736
Comment:
Revision 10 as of 2020-08-28 09:29:22
Size: 2478
Editor: naohisa.sato
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:

 * Cable preparation for yaw stepper motor [Sato]

  * The five cables requested will be ordered in early October. But how about the following alternatives using the cables we already have.

   * For four (50 cm , kapton, M-Dsub<>bundy plug) cables. We have six unused cables of different lengths with similar specifications.([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|JGW-D1503901/24]])

   * For (2.5m, F-Dsub<>F-Dsub) cable. We have Type2-2m(Dsub F-F, kapton) and Type4-1m(Dsub F-M, kapton). Two cables can be connected and extended.

Line 20: Line 30:
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A tower]]   * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A tower installation]]
Line 25: Line 35:
 * Acceptance Test ([[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/Acceptance%20Test|Wiki page]]).
Line 32: Line 43:
 * [Ishizaki] GAS filter improvement for post O4.  * [Ishizaki] GAS filter improvement for post O4.[[attachment:slide.pdf]]

Agenda/Minutes of the VIS Meeting on 2020/8/28

2020/8/28 14:00 -

Zoom Meeting

Participants:

Progress report

General

Type-A

Type-B

  • Cable preparation for yaw stepper motor [Sato]
    • The five cables requested will be ordered in early October. But how about the following alternatives using the cables we already have.
      • For four (50 cm , kapton, M-Dsub<>bundy plug) cables. We have six unused cables of different lengths with similar specifications.(JGW-D1503901/24)

      • For (2.5m, F-Dsub<>F-Dsub) cable. We have Type2-2m(Dsub F-F, kapton) and Type4-1m(Dsub F-M, kapton). Two cables can be connected and extended.

Type-Bp

Type-C

Controls

Electronics

Towards O4

cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List)

Safety

Discussion

  • [Terrence] New features for the suspensions, type-A and type-B, as pre-O4 upgrades (II).
  • [Ishizaki] GAS filter improvement for post O4.slide.pdf

Travel Plans

Next meeting

  • On 2020/9/4(Fri)

KAGRA/Subgroups/VIS/VISMinutes20200828 (last edited 2020-08-28 16:24:02 by RyutaroTakahashi)