2020/9/25 13:00 - | 2020/9/25 13:00 - |
Line 6: | Line 6: |
Participants: | Participants: |
Line 15: | Line 15: |
=== Type B === | * [Fujii] Can you please update the status of paper writing especially about the Type-A mechanics and its control? I also would like to know the rough schedule that you team are planning. Please let me know. Leaving your comments here will be enough. O-tsu-ka-re-sa-ma-de-su. (My account will have to be removed I guess btw..) === Type-B === * [Sato] Design of the limit switches for BS IP FR. [[attachment:BS IP FR limit switch_20200924.pdf]] * I submitted the paper to C&QG, finally. * Hirata-san and I had an information session for Washimi-san. * I asked to Takahashi-san for some long poles to mount the dial gauges around outer frames. Maybe there are some in TAMA. Work in progress. * Given the new temperature conditions in the central room, I offloaded fishing rods: * SR2 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15081|15081]]) and SRM (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15083|15083]]) fishing rods are working well. * BS: F0 and BF fishing rods look healthy and F1 one is at the bottom of its range (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15071|15071]]). * SR3: F0 fishig rod is healthy, the F1 one is still jammed and BF one at its upper limit (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15070|15070]]). * I changed some DC filters setpoint and updated BURT and SDF files. In SR3 I keep the height of the mirror constant. * For SR3 F1, I calculated the amount of ballast the needs to be removed to bring it to nominal height: 31 grams or less (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15102|15102]]). This number has be reviewed once I calculate how much mass we need to remove from the IM. The BF fishing rod needs to be in mid-range with control off to know. * Next week: * Same calculation for the other filters: they require setting the fishing rods to mid-range. * With the new temperature conditions I need to measure IP resonant frequencies again. * LVDT card document |
Line 20: | Line 37: |
Line 22: | Line 38: |
* KAGRA is in "RSE Trial" now. | * KAGRA is in "RSE Trial" now. "SEO is thinking about possibility for one week extension and the schedule reconstruction for vacuum chamber opening." |
Line 27: | Line 43: |
* When you make inventories, indicate [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0119/E2011960/002/KAGRA_Cleanbooth_Segment_Name.pdf|the segment name]]. * Schedule |
* Inventory sheet with [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0119/E2011960/002/KAGRA_Cleanbooth_Segment_Name.pdf|the segment name]] is necessary ([[https://www.dropbox.com/s/uz1ial5r377dgvt/Inventory%20check.xlsx?dl=0|Example of Type-A]]). * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Schedule]] |
Line 36: | Line 52: |
* Criteria in the acceptance test [[https://www.dropbox.com/s/pc9y3im2v4yvz6n/Acceptance%20test%20criteria.xlsx?dl=0|Sheet]]. * Presentation * PAB (10/8) * Chief Meeting (10/12) |
|
Line 39: | Line 59: |
* [Terrence] VIS health checking system [[https://github.com/gw-vis/vishack|VISHack]] |
Agenda/Minutes of the VIS Meeting on 2020/9/25
2020/9/25 13:00 -
Participants:
Interface VIS+CRY
- Schedule
Progress report
General
Type-A
- [Fujii] Can you please update the status of paper writing especially about the Type-A mechanics and its control? I also would like to know the rough schedule that you team are planning. Please let me know. Leaving your comments here will be enough. O-tsu-ka-re-sa-ma-de-su. (My account will have to be removed I guess btw..)
Type-B
[Sato] Design of the limit switches for BS IP FR. BS IP FR limit switch_20200924.pdf
I submitted the paper to C&QG, finally.
- Hirata-san and I had an information session for Washimi-san.
- I asked to Takahashi-san for some long poles to mount the dial gauges around outer frames. Maybe there are some in TAMA. Work in progress.
- Given the new temperature conditions in the central room, I offloaded fishing rods:
SR2 (klog 15081) and SRM (klog 15083) fishing rods are working well.
BS: F0 and BF fishing rods look healthy and F1 one is at the bottom of its range (klog 15071).
SR3: F0 fishig rod is healthy, the F1 one is still jammed and BF one at its upper limit (klog 15070).
- I changed some DC filters setpoint and updated BURT and SDF files. In SR3 I keep the height of the mirror constant.
For SR3 F1, I calculated the amount of ballast the needs to be removed to bring it to nominal height: 31 grams or less (klog 15102). This number has be reviewed once I calculate how much mass we need to remove from the IM. The BF fishing rod needs to be in mid-range with control off to know.
- Next week:
- Same calculation for the other filters: they require setting the fishing rods to mid-range.
- With the new temperature conditions I need to measure IP resonant frequencies again.
- LVDT card document
Type-Bp
Type-C
Controls
Electronics
Towards O4
- KAGRA is in "RSE Trial" now. "SEO is thinking about possibility for one week extension and the schedule reconstruction for vacuum chamber opening."
- Preparation work.
- The preparation work will be started on Oct. 1st.
Inventory sheet with the segment name is necessary (Example of Type-A).
- Procedure documents.
Criteria in the acceptance test Sheet.
- Presentation
- PAB (10/8)
- Chief Meeting (10/12)
Safety
Discussion
[Terrence] VIS health checking system VISHack
Travel Plans
The week from 9/28
- Takahashi: 9/30-10/2
- Sato: 9/30-10/2
- Hirata: 9/30-10/2
The week from 10/5
- Takahashi: 10/5-9
- Sato: 10/5-9
- Hirata: 10/5-9
Next meeting
- On 2020/10/2(Fri)