Differences between revisions 3 and 13 (spanning 10 versions)
Revision 3 as of 2020-09-24 21:35:47
Size: 2276
Comment:
Revision 13 as of 2020-09-25 10:58:19
Size: 2921
Comment:
Deletions are marked like this. Additions are marked like this.
Line 15: Line 15:
 * [Fujii] Can you please update the status of paper writing especially about the Type-A mechanics and its control? I would like to know the rough schedule that you team are planning. Please let me know. Leaving your comments here will be enough. O-tsu-ka-re-sa-ma-de-su.  * [Fujii] Can you please update the status of paper writing especially about the Type-A mechanics and its control? I also would like to know the rough schedule that you team are planning. Please let me know. Leaving your comments here will be enough. O-tsu-ka-re-sa-ma-de-su. (My account will have to be removed I guess btw..)
Line 18: Line 18:
 * [Sato] Design of the limit switches for BS IP FR. [[attachment:BS IP FR limit switch_20200924.pdf]]
Line 24: Line 26:
 * KAGRA is in "RSE Trial" now.  * KAGRA is in "RSE Trial" now. "SEO is thinking about possibility for one week extension and the schedule reconstruction for vacuum chamber opening."
Line 29: Line 31:
  * When you make inventories, indicate [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0119/E2011960/002/KAGRA_Cleanbooth_Segment_Name.pdf|the segment name]].
 * Schedule
  * Inventory sheet with [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0119/E2011960/002/KAGRA_Cleanbooth_Segment_Name.pdf|the segment name]] is necessary ([[https://www.dropbox.com/s/uz1ial5r377dgvt/Inventory%20check.xlsx?dl=0|Example of Type-A]]).
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Schedule]]
Line 38: Line 40:
 * Criteria in the acceptance test [[https://www.dropbox.com/s/pc9y3im2v4yvz6n/Acceptance%20test%20criteria.xlsx?dl=0|Sheet]].
 * Presentation
  * PAB (10/8)
  * Chief Meeting (10/12)

Agenda/Minutes of the VIS Meeting on 2020/9/25

2020/9/25 13:00 -

Zoom Meeting

Participants:

Interface VIS+CRY

Progress report

General

Type-A

  • [Fujii] Can you please update the status of paper writing especially about the Type-A mechanics and its control? I also would like to know the rough schedule that you team are planning. Please let me know. Leaving your comments here will be enough. O-tsu-ka-re-sa-ma-de-su. (My account will have to be removed I guess btw..)

Type-B

Type-Bp

Type-C

Controls

Electronics

Towards O4

Safety

Discussion

Travel Plans

The week from 9/28

  • Takahashi: 9/30-10/2
  • Sato: 9/30-10/2
  • Hirata: 9/30-10/2

The week from 10/5

  • Takahashi: 10/5-9
  • Sato: 10/5-9
  • Hirata: 10/5-9

Next meeting

  • On 2020/10/2(Fri)