Size: 2282
Comment:
|
Size: 2488
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 21: | Line 21: |
* Sugiyama-san(ICRR, Uchiyama Lab.) will join VIS group, mainly for reinstallation of Type-A tower in Y-end. * [Takahashi, Miyo, Ikeda] We plan to test the heater control at the cross tube in IX or IY. |
Agenda/Minutes on 2020/10/2
CRY+VIS Interface Meeting
13:30-
Participants:
Cable bandling bellow BF.Cable bandling BF-CRYO.pdf
VIS Meeting
14:00-
Participants:
Progress report
General
- Sugiyama-san(ICRR, Uchiyama Lab.) will join VIS group, mainly for reinstallation of Type-A tower in Y-end.
- [Takahashi, Miyo, Ikeda] We plan to test the heater control at the cross tube in IX or IY.
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- RSE Trial was extended to Oct. 7th.
- Preparation work.
- The preparation work will be started on Oct. 8th.
- Inventory sheet.
- Cable removal.
- Procedure documents.
- Criteria in the acceptance test.
- Presentation
- PAB (10/8)
- Chief Meeting (10/12)
Safety
Discussion
Travel Plans
The week from 10/5
- Takahashi: 10/7-10/9
- Sato: 10/7-10/9
- Hirata: 10/7-10/9
The week from 10/12
- Takahashi: 10/12-16
- Sato: 10/12-16
- Hirata: 10/12-16
Next meeting
- On 2020/10/9(Fri)