Agenda/Minutes on 2020/10/16
CRY+VIS Interface Meeting
13:30-
Participants:
- Cable bandling bellow BF.
VIS Meeting
14:00-
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- RSE Trial was finished on Oct. 13th.
- Preparation work is on going.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 10/19
- Takahashi: 10/19-10/23
The week from 10/26
- Hirata: ?
Next meeting
- On 2020/10/23(Fri)