= Agenda/Minutes on 2020/10/30 = [[https://zoom.us/j/203743987|Zoom Meeting]] = CRY+VIS Interface Meeting = 13:00-13:50 Participants: Takahashi, Sato, Hirata, Miyo, Ikeda, Aso, Ushiba, Kimura, Shoda, Hagiwara * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Upgrades/PostO3Upgrades|Post O3 Upgrade portal]] * Schedule: Wire disconnection (IX 11/13, EX 11/19), WAB safe mode (10/26-11/13). * Jig for the FC painting. LED light is necessary. * IP monitoring in the next venting on 11/4 and 11/20. * PF actuator: Measurement of coefficients and calculation of the noise (by mid Dec.). * Time of this meeting. 13:30 to 14:00, extended to 14:30. = VIS Meeting = 14:00-15:00 Participants: Takahashi, Hirata, Aso, Shoda, Miyo, Sato, Fabian, Terrence, Sugiyama, Tanaka == Progress report == === General === === Type-A === * Tested the ribbon heaters in the X-end. The heaters on the cross tube ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15346|klog]]) and top chamber ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15338|klog]]) affected the height of F3/BF and F0 respectively. The temperature of BF was changed little (<0.1deg). The temperature control of heater itself is meaningful to keep the height of GAS filters. === Type-B === [Fabian] * I watched Mirapro removed the bellows and ducts, especially around BS, wich still has its oplev. Everything seemed alright. Let us measure TFs once the DGS is recovered. * I asked Uchiyama-san about the BS outter frame beams. He will talk about this with Mirapro next week. * Hirata-san picked up some components, which we will use in vacuum, in order to wash them in Mitaka. * Hirata-san brought into the mine the BS and SR IP fixing jig and F0 top plate replacement. * '''Why do we need to IP fixing jig for SR? I think we need it only for BS because we will remove the IP LVDTs<
>''' * Venting finished on Monday. The buoyancy effect on keystones was reported in klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15322|15322]]. This is very useful information for BS and SR3 work. * Once Mirapro removed the hatch doors in BS chamber that are at the BF level, I took a look and identified places to put the ballast masses. See klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15353|15353]]. Possible ctivities for the next weeks (subject to Takahashi-san's approval): * Shimode-san and Yokozawa-san need to inspect SR3 and SR2 racks. I'll help them with that. * Visual inspection of SRM IM looking for a cable pulling. * Removing clamps from the vacuum chambers caps. Mirapro will not do it. People without hernia are required. * Opening of SRM side door. People without hernia are required. * Move IP ballast masses to the 2nd floor of the clean room. * Prepare pallet (or plastic beam replacement) for BS chamber cap. * Recovery of oplevs. * Measurement of gain resistances and phases in LVDT cards. * On BS BF filter, some ballast masses are fastened with a '''very long screw. Because we will add mass there, it would be good to estimate the length of the screw for preparation.''' In order to place a ruler next to it safely, it would be good to open the chamber and lock the IP, together with the BF cap. === Type-Bp === * Hirata-san talked with Shoda-san about how to check Traverser cables. * Mirapro removed ducts and bellows. === Type-C === * [Sato] IMMT2 modification parts was delivered at Oct.28. === Controls === === Electronics === * Asking the quotation for the test boards. Some parts would be delay. == Towards O4 == * Chamber opening and DGS update are on going. * Schedule. * Arrangement of personnel in Nov. ([[https://www.dropbox.com/s/ow2fvqozua9vghi/VIS%20schedule%20Nov.xlsx?dl=0|table]]) * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|VIS]] * Procedure documents. * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A tower installation]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11598|Limit switches]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11520|Limit switch connecting guide]] <-- revised by Ikeda-san * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11978|Replacement of TF blades]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11878|Wire gluing in PR3]] * [[https://onedrive.live.com/?authkey=!AOLVVVKJ_Zpn-2c&cid=1447B05D5B571A84&id=1447B05D5B571A84!26691&parId=1447B05D5B571A84!26683&o=OneUp|Type-B remedying work]] * Criteria in the acceptance test. == Safety == == Discussion == == Travel Plans == The week from 11/2 * Takahashi: 11/1-6 * Sato: 11/1-6 * Hirata: 11/1-6 The week from 11/9 * Takahashi: 11/9-13 * Sato: 11/9-12 * Hirata: 11/9-13 == Next meeting == * On 2020/11/6(Fri)