Agenda/Minutes on 2020/11/6
CRY+VIS Interface Meeting
13:30-
Participants:
- Cryo-payload was disconnected on 3rd and the wire was taken down under the cross tube on 5th in Y-end.
- Schedule: Wire disconnection (IX 11/13, EX 11/19), WAB safe mode (10/26-11/13).
- Jig for the FC painting.
- IP monitoring on 11/8(EX) and 11/20(IY).
- PF actuator: Measurement of coefficients and calculation of the noise (by mid Dec.).
VIS Meeting
14:00-
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- DGS update are on going.
- Schedule.
- Procedure documents.
Limit switches <-- Revised. Small changes in assembly (add one more nut)
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 11/9
- Takahashi: 11/9-13
- Sato: 11/9-12
- Hirata: 11/9-13
The week from 11/16
- Takahashi: 11/16-20
- Sato: 11/16-20
- Hirata: 11/16-20
Next meeting
- On 2020/11/13(Fri)