Differences between revisions 2 and 3
Revision 2 as of 2020-11-12 15:27:50
Size: 2105
Editor: naohisa.sato
Comment:
Revision 3 as of 2020-11-12 15:28:35
Size: 2112
Editor: naohisa.sato
Comment:
Deletions are marked like this. Additions are marked like this.
Line 57: Line 57:
 * Sato: ?  * Sato: 11/24-27

Agenda/Minutes on 2020/11/13

Zoom Meeting

CRY+VIS Interface Meeting

13:30-14:00

Participants:

  • Post O3 Upgrade portal

  • Disassembly of the Type-A tower was finished in Y-end (11/11).
  • Schedule: Wire disconnection (IX 11/13, EX 11/19), Chamber evacuation (IY 11/20).
  • Jig for the FC painting.
  • PF actuator: Measurement of coefficients --> calculation of the noise (by mid Dec.).

VIS Meeting

14:00-

Participants:

Progress report

General

Type-A

Type-B

Type-Bp

Type-C

  • [Sato](no progress)

Controls

Electronics

Towards O4

Safety

Discussion

Travel Plans

The week from 11/16

  • Takahashi: 11/16-20
  • Sato: 11/16-20
  • Hirata: 11/16-20

The week from 11/23

  • Aso: 11/24-27
  • Takahashi: 11/24-27
  • Hirata: 11/24-27
  • Sato: 11/24-27

Next meeting

  • On 2020/11/20(Fri)

KAGRA/Subgroups/VIS/VISMinutes20201113 (last edited 2020-11-13 15:19:31 by RyutaroTakahashi)