Agenda/Minutes on 2020/11/27

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

  • Post O3 Upgrade portal

  • Leak test of EYC.
  • Evacuation of IYC.
  • Jig for the FC painting.
  • The next connection/disconnection schedule.
  • PF actuator: Measurement of coefficients --> calculation of the noise (by mid Dec.).

VIS Meeting

14:00-

Participants:

Progress report

General

Type-A

Type-B

Type-Bp

Type-C

Controls

Electronics

Towards O4

Safety

Discussion

Travel Plans

The week from 11/30

  • Takahashi: 11/30-12/4
  • Hirata: 11/30-12/4
  • Sato: ?

The week from 12/7

  • Takahashi: 12/7-11
  • Hirata: 12/7-11

Next meeting

  • On 2020/12/4(Fri)