Differences between revisions 10 and 11
Revision 10 as of 2020-12-03 21:22:20
Size: 2299
Comment:
Revision 11 as of 2020-12-04 11:34:48
Size: 2333
Comment:
Deletions are marked like this. Additions are marked like this.
Line 49: Line 49:
 * Mechanical resonances of SRM.

Agenda/Minutes on 2020/12/4

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

  • Schedule: Upgrade work in IX (2/22-3/10) will be swapped with the work in EX (1/4-1/22). The connection of ITMX is available on 1/12.
  • Jig for the FC painting.
  • Acceptance check items.
  • PF actuator: Measurement of coefficients --> calculation of the noise (by the end of Jan.).

VIS Meeting

14:00-

Participants:

Progress report

General

Type-A

Type-B

Type-Bp

Type-C

  • Set up the old OSTM suspension in the OMC both.

Controls

Electronics

  • Tested the modified LVDT card. This modification (#14 pin grounded) will be applied to 16 cards.

Towards O4

Safety

Discussion

  • Mechanical resonances of SRM.

Travel Plans

The week from 12/7

  • Takahashi: 12/7-11
  • Hirata: 12/7-11

The week from 12/14

  • Takahashi: 12/14-18
  • Hirata: 12/14-18

(F2F Meeting in 17-18)

Next meeting

  • On 2020/12/11(Fri)

KAGRA/Subgroups/VIS/VISMinutes20201204 (last edited 2020-12-04 15:23:41 by RyutaroTakahashi)