Differences between revisions 19 and 23 (spanning 4 versions)
Revision 19 as of 2020-12-04 12:20:25
Size: 2828
Editor: KousekiMiyo
Comment:
Revision 23 as of 2020-12-04 12:36:13
Size: 3606
Editor: KousekiMiyo
Comment:
Deletions are marked like this. Additions are marked like this.
Line 24: Line 24:
As you all know, we have had trouble starting a measurement with a DGS error [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15567|klog#15567]]. In order to eliminate this confusion during the work, I make the following rules;
 * First, make sure that the VIS_OVERVIEW screen shows '''all green before you start working'''.
 * And after working, be sure to '''make everything green''' before finish your work. This is a kindness for the next operator.
 * The SDF will probably turn red as you work. This means that SDF has detected channel differences during your work. If you accept these differences, please '''take a screenshot and post it in klog''' (e.g. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15553|klog#15553]]), but you don't have to post it to revert.

That's all.

Agenda/Minutes on 2020/12/4

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

  • Schedule: Upgrade work in IXV (2/22-3/10) will be swapped with the work in EXV (1/4-1/22). The connection of ITMX is available on 1/12.
  • Jig for the FC painting.
  • Acceptance check items (Inspection document).

  • PF actuator: Measurement of coefficients --> calculation of the noise (by the end of Jan.).

VIS Meeting

14:00-

Participants:

Progress report

General

[Miyo] As you all know, we have had trouble starting a measurement with a DGS error klog#15567. In order to eliminate this confusion during the work, I make the following rules;

  • First, make sure that the VIS_OVERVIEW screen shows all green before you start working.

  • And after working, be sure to make everything green before finish your work. This is a kindness for the next operator.

  • The SDF will probably turn red as you work. This means that SDF has detected channel differences during your work. If you accept these differences, please take a screenshot and post it in klog (e.g. klog#15553), but you don't have to post it to revert.

That's all.

Type-A

Type-B

Type-Bp

Type-C

  • Set up the old OSTM suspension in the OMC both.
  • [Miyo] We (mainly Ikeda-san) made Type-C guardian. Now we can use ALIGN state. In this state, we only engage the APTICALIGN with ramp time not engage the OpLev DC control according to Nakano-san's advices. klog#15578

Controls

[Miyo]

Electronics

  • Tested the modified LVDT card. This modification (#14 pin grounded) will be applied to 16 cards.

Towards O4

Safety

Discussion

  • Mechanical resonances of SRM.

Travel Plans

The week from 12/7

  • Takahashi: 12/7-11
  • Hirata: 12/7-11
  • Yano: 12/7-11

The week from 12/14

  • Takahashi: 12/14-18
  • Hirata: 12/14-18
  • Yano: 12/14-18

(F2F Meeting in 12/17-18)

Next meeting

  • On 2020/12/11(Fri)

KAGRA/Subgroups/VIS/VISMinutes20201204 (last edited 2020-12-04 15:23:41 by RyutaroTakahashi)