Agenda/Minutes on 2020/12/4
CRY+VIS Interface Meeting
13:30-
Participants:
- Schedule: Upgrade work in IX (2/22-3/10) will be swapped with the work in EX (1/4-1/22). The connection of ITMX is available on 1/12.
- Jig for the FC painting.
- Acceptance check items.
PF actuator: Measurement of coefficients --> calculation of the noise (by the end of Jan.).
VIS Meeting
14:00-
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B remedy work is on going.
- Schedule.
Upgrade work in IX (2/22-3/10) will be swapped with the work in EX (1/4-1/22). (Chart)
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 12/7
- Takahashi: 12/7-11
- Hirata: 12/7-11
The week from 12/14
- Takahashi: 12/14-18
- Hirata: 12/14-18
(F2F Meeting in 17-18)
Next meeting
- On 2020/12/11(Fri)