Differences between revisions 1 and 2
Revision 1 as of 2020-12-09 20:27:41
Size: 2096
Comment:
Revision 2 as of 2020-12-09 20:28:42
Size: 2091
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:
 * Jig for the FC painting: Preparation for both sides.  * Jig for FC painting: Application to both sides.

Agenda/Minutes on 2020/12/11

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

  • Schedule: The connection of ITMX after 1/12.
  • Jig for FC painting: Application to both sides.
  • Acceptance check items: Flow chart.
  • PF actuator: Measurement of coefficients --> calculation of the noise (by the end of Jan.).

VIS Meeting

14:00-

Participants:

Progress report

General

Type-A

Type-B

Type-Bp

Type-C

Controls

Electronics

Towards O4

Safety

Discussion

Travel Plans

The week from 12/14

  • Takahashi: 12/14-18
  • Hirata: 12/14-18
  • Yano: 12/14-18

The week from 12/21

  • Takahashi: 12/21-25
  • Hirata: 12/21-25
  • Yano: 12/21-25

(F2F Meeting in 12/17-18)

Next meeting

  • On 2020/12/25(Fri)

KAGRA/Subgroups/VIS/VISMinutes20201211 (last edited 2020-12-12 10:52:08 by RyutaroTakahashi)