Line 12: Line 12:
 * Jig for the FC painting: Preparation for both sides.  * Jig for FC painting: Application to both sides.
Line 24: Line 24:
 * Modified three ACCs. The capacitance sensors were replaced to the LVDTs.
Line 55: Line 57:
(F2F Meeting in 12/17-18)
Line 57: Line 61:
 * Takahashi: 12/21-25
 * Hirata: 12/21-25
 * Yano: 12/21-25

(F2F Meeting in 12/17-18)
 * Takahashi: 12/21-24
 * Hirata: 12/21-24
 * Yano: 12/21-24

Agenda/Minutes on 2020/12/11

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

  • Schedule: The connection of ITMX after 1/12.
  • Jig for FC painting: Application to both sides.
  • Acceptance check items: Flow chart.
  • PF actuator: Measurement of coefficients --> calculation of the noise (by the end of Jan.).

VIS Meeting

14:00-

Participants:

Progress report

General

Type-A

  • Modified three ACCs. The capacitance sensors were replaced to the LVDTs.

Type-B

Type-Bp

Type-C

Controls

Electronics

Towards O4

Safety

Discussion

Travel Plans

The week from 12/14

  • Takahashi: 12/14-18
  • Hirata: 12/14-18
  • Yano: 12/14-18

(F2F Meeting in 12/17-18)

The week from 12/21

  • Takahashi: 12/21-24
  • Hirata: 12/21-24
  • Yano: 12/21-24

Next meeting

  • On 2020/12/25(Fri)

KAGRA/Subgroups/VIS/VISMinutes20201211 (last edited 2020-12-12 10:52:08 by RyutaroTakahashi)