= Agenda/Minutes on 2021/1/22 =
[[https://zoom.us/j/203743987|Zoom Meeting]]

= CRY+VIS Interface Meeting =
13:30-14:00

Participants: Takahashi, Sato, Hirata, Ikeda, Miyo, Ushiba, Tomaru, Kimura, Aso

[[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Upgrades/PostO3Upgrades|Post O3 Upgrade portal]]

 * Schedule for IX: Cabling for the payload is scheduled from 1/26. Connection is scheduled in the week of 2/8.
 * Schedule for IY: Cooling of payload was started from 1/18.
 * Schedule for EX: Connection of ETMX was scheduled in the week of 3/15.
 * Corrugate tube fixing jig: Re-measurement at the beginning of March (3/1-3) in IYV is planed. Deformation of the bottom ring of top-chamber would be large.
 * Commissioning in vacuum:
 * Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.  
 * Jig for FC painting: Under manufacturing.
 * PF actuator: by the end of January.

= VIS Meeting =
14:00-15:30

Participants: Takahashi, Sato, Hirata, Miyo, Aso, Iguchi, Ishizaki, Tanaka, Washimi, Terrence

== Progress report ==
=== General ===
=== Type-A ===
 * Installation in EYV.
  * Going to the F3 stage.
  * Blades for FR in the F3 was replaced. Checked the motion of FR.
  * Measured the spectrum of BF LVDT.
  * Mounted the F3 on the EQ stop. The BF was suspended by the F3.
  * Prepared the cables between the BF and F3.
  * The cabling work from BF to F3 was completed.

 * Stepper motor driver in EYV
  * One channel of the stepper motor driver for GAS had failed. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15785|k-log]]

=== Type-B ===
Albums

 * [[https://photos.app.goo.gl/YiRfy6a9uDf4rvcKA|BS remedying work after O3]]
 * [[https://photos.app.goo.gl/4cvWnXCdCsf9WiYf7|SR2 remedying work after O3]]
 * [[https://photos.app.goo.gl/X2eaBxsZGaRHYAQK6|SR3 remedying work after O3]]
 * [[https://photos.app.goo.gl/6C5tGpn7CLgGUG9y6|SRM remedying work after O3]]

Week of the 18th of January

Hirata-san worked in the design of the thermistor holder, cabling, etc.

SRM

I disconnected SRM picomotor drivers to move them away from the assembly frame. I failed to report it in a klogin due time.

BS

 * Miyo-kun,  Hirata-san and I reviewed the IP transformation matrices from IP LVDTs  to L, T and Y and from actuation in L, T and Y to real coil-magnet  actuator. We found a few of inconsistencies in existing documents. See  klog reports [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15769|15769]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15776|15776]].
 * We recovered the IP alignment:
  * See klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15782|15782]].
  * I updated the medm screen with these matrices. Diagonalization is pending.
  * I moved the IP close to the setpoint using horizontal FRs.
  * I  turned the control system on by hand and works fine. (I tried using  Guardian but it keeps using the old setpoint values despite I took a  snapshot.)
  * I moved BF  keystone to around zero. (F1 keystone has been in midrange for a long  time and we should not move it unless it's absolutely necessary.)
  * We  went to the tunnel and recovered the oplev readout. We had to move the  suspension in yaw by a lot (mrad maybe) using the new F0-Y stepper  motor.
  * After recovery I  measured TFs in the IP. They look fine, but in IP-L and IP-T the  coherence is low from 150 mHz to 400 mHz. Terrence suggested to check  coherence with ground motion and we cna also increase the amount of  actuation.
 * We finally got to add ballast mass on top of BF:
  * When we began working the temperature was 23.1 degrees but when we finished it was 23.5 degrees ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15809|klog 15809]]), likely due to the coach filters ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15810|klog 15810]]), but this morning it was 23.0 degrees.
  * The  final result is that the keystone is now about 16 um above the goal. It  requires -1,100 counts of coil-magnet actuation to reach it. After pump  down we can use the FR to move it closer if we think it's suitable.
  * The aligmment of the OSEMs didn't change much.
  * IM TF measuements reveal that the system is healthy.
 * Things left to do in BS suspension:
  * In F0 adjust ballast mass, FR position and limit switch positions.
  * Tune IP resonant frequency.
  * Measure IP-LVDT sensitivity.
  * Install oplev box (what is the status?)
  * Install outer frame large beam? (what is the status?)

Plan for next week

SR3

 * Alignment recovery after cabling (it seems they want to use it next week for injecting green light.)
 * Preparation for ballas mass adjustment.

=== Type-Bp ===
[Fabian] What's the plan for next week? It is something like this:

 * Traverser cable change?
 * Gluing wire in PR3?

=== Type-C ===
=== Controls ===
Although I told you that I explain my document for Suspension Commissioning, I should write more information.
[[https://docs.google.com/document/d/1LfWFfzdWr6xrGkzuy5gLxuKQ3hOtdXHswb2HeZFqrtE/edit?usp=sharing|here]]

=== Electronics ===
 * Compared the TFs of modified LVDT board with the original board. Reduction of 50dB in the TF was found.
 * Actual effect should be measured using the BF damper in PR.

== Towards O4 ==
 * Type-B remedy work is on going.
 * Installation of Type-A is on going in EY.
 * Schedule.
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Chart]]
 * Procedure documents.
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A tower installation]]
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11598|Limit switches]]
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11520|Limit switch connecting guide]]
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11978|Replacement of TF blades]]
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11878|Wire gluing in PR3]]
  * [[https://onedrive.live.com/?authkey=!AOLVVVKJ_Zpn-2c&cid=1447B05D5B571A84&id=1447B05D5B571A84!26691&parId=1447B05D5B571A84!26683&o=OneUp|Type-B remedying work]]
 * Criteria in the acceptance test.
  * [[https://www.dropbox.com/s/6bv15yy6hg0wn40/Acceptance%20Test%20Documentation.docx?dl=0|Inspection document (sample)]]

== Safety ==
== Discussion ==
 * BS control noise

== Travel Plans ==
The week from 1/25

 * Takahashi: 1/25-29
 * Sato: 1/25-29
 * Hirata: 1/25-29
 * Yano: 1/25-29

The week from 2/1

 * Takahashi: 2/1-5
 * Sato: 2/1-5
 * Hirata: 2/1-5
 * Yano: 2/1-5

== Next meeting ==
 * On 2020/1/29(Fri)