Differences between revisions 14 and 16 (spanning 2 versions)
Revision 14 as of 2021-01-29 11:54:31
Size: 4636
Editor: KousekiMiyo
Comment:
Revision 16 as of 2021-01-29 11:58:19
Size: 4722
Editor: KousekiMiyo
Comment:
Deletions are marked like this. Additions are marked like this.
Line 37: Line 37:
 * Ikeda-san found that the toggle switch of the stepper motor driver was turned on, which means that the motor driver works as "test mode". According to his statement, in this mode, we can not turn off the driver power in remotely. In fact, if the switch is turned up meaning the test mode, BIO signal is shorted to the ground according to [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5366|JGW-D1605366-v1]] Then, he checked the status of the switch in all area. He found that some switch was on and turn off these switch for remote operation [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15854|klog#15854]].  * Ikeda-san found that the toggle switch of the stepper motor driver was turned on, which means that the motor driver works as "test mode". According to his statement, in this mode, we can not turn off the driver power in remotely. In fact, '''if the switch is turned up meaning the test mode, BIO signal is shorted to the ground according to [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5366|JGW-D1605366-v1]].''' Then, he checked the status of the switch in all area. He found that some switch was on and turn off these switch for remote operation [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15854|klog#15854]]. Additionally, BS wasn't even cabling according to Ikeda-san. It should be done.

Agenda/Minutes on 2021/1/29

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

  • Schedule for IX: Connection is scheduled in the week of 2/8.
  • Schedule for IY: Disconnection was scheduled on 3/11.
  • Schedule for EX: Connection was scheduled in the week of 3/15.
  • Corrugate tube fixing jig: Re-measurement is planed in 2/28-3/2 at IYV.
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
  • Jig for FC painting: Under manufacturing.
  • PF actuator: by the end of January.
    • [Miyo] Although this project must start after we define the actuator efficiency of PF, I (Miyo) have not defined yet. Progress is here.

VIS Meeting

14:00-

Participants:

Progress report

General

  • O3GK Noise Budget paper [Washimi] : The paper writing team (Kokeyama, KYamamoto, Washimi) is writing the draft.
    • Seismic noise through Type-A tower : on going
      • This noise is evaluated by the TF (Shoda-san's simulation). -> Does it include the actual situation of GAS filters? -> Maybe "yes" (by Miyo-kun)

    • Type-A ctrl : on going
    • Type-B ctrl : almost written. Please check it.
    • Type-Bp ctrl : almost written. Please check it.

[Miyo]

  • In order to resolve unstable network trouble of picomotor drivers that have been going on for a long time, Ikeda-san is investigating the network connection under the DGS network. He have completed to make a network diagram in this week. Report for the investigation is uploaded in JGW-E2112439. Because we found the network is too messy to manage, we separate the network for the drivers including stepper motors from the other equipments e.g. workstation. So, we are planning to make new independent network for the drivers. In this new network, drivers and script machine named k1script (now we are change to k1script1 which can run Python3 environment) will be only connected. We now think we can improve the network trouble should be resolved.

  • Ikeda-san found that the toggle switch of the stepper motor driver was turned on, which means that the motor driver works as "test mode". According to his statement, in this mode, we can not turn off the driver power in remotely. In fact, if the switch is turned up meaning the test mode, BIO signal is shorted to the ground according to JGW-D1605366-v1. Then, he checked the status of the switch in all area. He found that some switch was on and turn off these switch for remote operation klog#15854. Additionally, BS wasn't even cabling according to Ikeda-san. It should be done.

Type-A

  • Implemented the cabling for cryo-payload in IX.
  • Assembled the connector cables for ACCs.
  • Assembled the geophone pods for ITMY.

Type-B

Type-Bp

Type-C

Controls

Electronics

Towards O4

Safety

Discussion

  • Temperature setting around Type-B.

Travel Plans

The week from 2/1

  • Takahashi: 2/1-5
  • Sato: 2/1-5
  • Hirata: 2/1-5
  • Yano: 2/1-5

The week from 2/8

  • Takahashi: 2/8-12
  • Sato: 2/8-12
  • Hirata: 2/8-12
  • Yano: 2/8-12

Next meeting

  • On 2020/2/5(Fri)

KAGRA/Subgroups/VIS/VISMinutes20210129 (last edited 2021-01-29 20:30:04 by RyutaroTakahashi)