Agenda/Minutes on 2021/1/29
CRY+VIS Interface Meeting
13:30-
Participants:
- Schedule for IX: Connection is scheduled in the week of 2/8.
- Schedule for IY: Disconnection was scheduled on 3/11.
- Schedule for EX: Connection was scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/28-3/2 at IYV.
- Commissioning in vacuum:
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- Jig for FC painting: Under manufacturing.
- PF actuator: by the end of January.
VIS Meeting
14:00-
Participants:
Progress report
General
- O3GK Noise Budget paper [Washimi] : The paper writing team (Kokeyama, KYamamoto, Washimi) is writing the draft.
- Seismic noise through Type-A tower : on going
This noise is evaluated by the TF (Shoda-san's simulation). -> Does it include the actual situation of GAS filters? -> Maybe "yes" (by Miyo-kun)
- Type-A ctrl : on going
- Type-B ctrl : almost written. Please check it.
- Type-Bp ctrl : almost written. Please check it.
- Seismic noise through Type-A tower : on going
Type-A
- Implemented the cabling for cryo-payload in IX.
- Assembled the connector cables for ACCs.
- Assembled the geophone pods for ITMY.
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
- Temperature setting around Type-B.
Travel Plans
The week from 2/1
- Takahashi: 2/1-5
- Sato: 2/1-5
- Hirata: 2/1-5
- Yano: 2/1-5
The week from 2/8
- Takahashi: 2/8-12
- Sato: 2/8-12
- Hirata: 2/8-12
- Yano: 2/8-12
Next meeting
- On 2020/2/5(Fri)