Describe KAGRA/Subgroups/VIS/VISMinutes20210205 here. | = Agenda/Minutes on 2021/2/5 = [[https://zoom.us/j/203743987|Zoom Meeting]] = CRY+VIS Interface Meeting = 13:30-14:00 Participants: [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Upgrades/PostO3Upgrades|Post O3 Upgrade portal]] Copy from previous meeting * Schedule for IX: Connection is scheduled in the week of 2/8. * Schedule for IY: Disconnection was scheduled on 3/11. * Schedule for EX: Connection was scheduled in the week of 3/15. * Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV. * Commissioning in vacuum: Two phased commissioning will be tried in IX at beginning. After that, one phase is default. * Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going. * Jig for FC painting: Under manufacturing. * PF actuator: by the end of January. * [Miyo] Although this project must start after we define the actuator efficiency of PF, I (Miyo) have not defined yet. Progress is [[https://github.com/gw-vis/SuspensionModel/issues/23|here]]. = VIS Meeting = 14:00-16:00 Participants: == Progress report == === General === === Type-A === === Type-B === === Type-Bp === === Type-C === === Controls === === Electronics === == Towards O4 == == Safety == == Discussion == == Travel Plans == == Next meeting == |
Agenda/Minutes on 2021/2/5
CRY+VIS Interface Meeting
13:30-14:00
Participants:
Copy from previous meeting
- Schedule for IX: Connection is scheduled in the week of 2/8.
- Schedule for IY: Disconnection was scheduled on 3/11.
- Schedule for EX: Connection was scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
- Commissioning in vacuum: Two phased commissioning will be tried in IX at beginning. After that, one phase is default.
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- Jig for FC painting: Under manufacturing.
- PF actuator: by the end of January.
[Miyo] Although this project must start after we define the actuator efficiency of PF, I (Miyo) have not defined yet. Progress is here.
VIS Meeting
14:00-16:00
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
Safety
Discussion
Travel Plans