Line 3: | Line 3: |
* 2021-01-29 08:59:00,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15864|15864]]: VIS/IX, '''takafumi.ushiba''', Comment to Cabling for cryo-payload (Click here to view original report: 15860) * 2021-01-29 21:19:00,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15866|15866]]: VIS/IX, '''ryutaro.takahashi''', Comment to Cabling for cryo-payload (Click here to view original report: 15860) * 2021-01-31 16:22:00,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15868|15868]]: VIS/General, '''kouseki.miyo''', Some suspensions are not SAFE. * 2021-01-31 17:00:00,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15869|15869]]: VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844) * 2021-01-31 18:41:00,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15871|15871]]: VIS/General, '''kouseki.miyo''', ISOLATED state is available with only LVDTs not blended sensors. |
* Friday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15864|15864]]: VIS/IX, '''takafumi.ushiba''', Comment to Cabling for cryo-payload (Click here to view original report: 15860) * Friday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15866|15866]]: VIS/IX, '''ryutaro.takahashi''', Comment to Cabling for cryo-payload (Click here to view original report: 15860) * Sunday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15868|15868]]: VIS/General, '''kouseki.miyo''', Some suspensions are not SAFE. * Sunday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15869|15869]]: VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844) * Sunday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15871|15871]]: VIS/General, '''kouseki.miyo''', ISOLATED state is available with only LVDTs not blended sensors. |
Contents
Activities in this week
Friday,15864: VIS/IX, takafumi.ushiba, Comment to Cabling for cryo-payload (Click here to view original report: 15860)
Friday,15866: VIS/IX, ryutaro.takahashi, Comment to Cabling for cryo-payload (Click here to view original report: 15860)
Sunday,15868: VIS/General, kouseki.miyo, Some suspensions are not SAFE.
Sunday,15869: VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)
Sunday,15871: VIS/General, kouseki.miyo, ISOLATED state is available with only LVDTs not blended sensors.
Agenda/Minutes on 2021/2/5
CRY+VIS Interface Meeting
13:30-14:00
Participants:
Copy from previous meeting
- Schedule for IX: Connection is scheduled in the week of 2/8.
- Schedule for IY: Disconnection was scheduled on 3/11.
- Schedule for EX: Connection was scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
- Commissioning in vacuum: Two phased commissioning will be tried in IX at beginning. After that, one phase is default.
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- Jig for FC painting: Under manufacturing.
- PF actuator: by the end of January.
VIS Meeting
14:00-16:00
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans