'''Tuesday''' * Tuesday, '''satoru.ikeda''', VIS/PR2, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857), [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15880|15880]] * Tuesday, '''takaaki.yokozawa''', PEM/Center, IXC, [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15881|15881]] * Tuesday, '''satoru.ikeda''', VIS/PR2, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857), [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15882|15882]] * Tuesday, '''takayuki.tomaru''', CRY/Cryostat IY, IYC test (temperature & frosting), [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15883|15883]] * Tuesday, '''rishabh.bajpai''', CRY/Cryostat IY, Vibration Analysis, [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15884|15884]] * Tuesday, '''satoru.ikeda''', VIS/PR3, Driveable range of the PR3 GAS SF stepper motor, [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15886|15886]] * Tuesday, '''kouseki.miyo''', VIS/General, All payload models are in PAYLOAD_MASTER.mdl, [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15888|15888]] * Tuesday, '''fabian.arellano''', VIS/PR3, Comment to Gluing the mirror wire. (Click here to view original report: 15844), [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15885|15885]] * Tuesday, '''fabian.arellano''', VIS/PR3, Traverser motor test and cabling., [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15889|15889]] * Tuesday, '''satoru.ikeda''', VIS/PR3, Comment to Traverser motor test and cabling. (Click here to view original report: 15889), [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15890|15890]] * Tuesday, '''ryutaro.takahashi''', VIS/EY, Setup of F3, [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15891|15891]] This text is generated by script in "/kagra/Dropbox/Personal/miyo/Scripts/klog/main.py". |
Contents
Activities in this week
Friday
Friday, takafumi.ushiba, VIS/IX, Comment to Cabling for cryo-payload (Click here to view original report: 15860), 15864
Friday, ryutaro.takahashi, VIS/IX, Comment to Cabling for cryo-payload (Click here to view original report: 15860), 15866
Sunday
Sunday, kouseki.miyo, VIS/General, Some suspensions are not SAFE., 15868
Sunday, fabian.arellano, VIS/PR3, Comment to Gluing the mirror wire. (Click here to view original report: 15844), 15869
Sunday, kouseki.miyo, VIS/General, ISOLATED state is available with only LVDTs not blended sensors., 15871
Monday
Monday, ryutaro.takahashi, VIS/OMM, Comment to Modification of ACCs (Click here to view original report: 15617), 15872
Monday, kouseki.miyo, VIS/General, Comment to Relay Switch of Stepper Motor Driver (Click here to view original report: 15847), 15873
Monday, fabian.arellano, VIS/PR3, Comment to Gluing the mirror wire. (Click here to view original report: 15844), 15875
Monday, satoru.ikeda, VIS/PR2, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857), 15876
Monday, satoru.ikeda, VIS/General, Comment to We investigated the network connection. (Click here to view original report: 15737), 15877
Monday, takafumi.ushiba, CRY/Cryo-payload EX, EX payload upgrade, 15878
Tuesday
Tuesday, satoru.ikeda, VIS/PR2, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857), 15880
Tuesday, takaaki.yokozawa, PEM/Center, IXC, 15881
Tuesday, satoru.ikeda, VIS/PR2, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857), 15882
Tuesday, takayuki.tomaru, CRY/Cryostat IY, IYC test (temperature & frosting), 15883
Tuesday, rishabh.bajpai, CRY/Cryostat IY, Vibration Analysis, 15884
Tuesday, satoru.ikeda, VIS/PR3, Driveable range of the PR3 GAS SF stepper motor, 15886
Tuesday, kouseki.miyo, VIS/General, All payload models are in PAYLOAD_MASTER.mdl, 15888
Tuesday, fabian.arellano, VIS/PR3, Comment to Gluing the mirror wire. (Click here to view original report: 15844), 15885
Tuesday, fabian.arellano, VIS/PR3, Traverser motor test and cabling., 15889
Tuesday, satoru.ikeda, VIS/PR3, Comment to Traverser motor test and cabling. (Click here to view original report: 15889), 15890
Tuesday, ryutaro.takahashi, VIS/EY, Setup of F3, 15891
This text is generated by script in "/kagra/Dropbox/Personal/miyo/Scripts/klog/main.py".
Agenda/Minutes on 2021/2/5
CRY+VIS Interface Meeting
13:30-14:00
Participants:
Copy from previous meeting
- Schedule for IX: Connection is scheduled in the week of 2/8.
- Schedule for IY: Disconnection was scheduled on 3/11.
- Schedule for EX: Connection was scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
- Commissioning in vacuum: Two phased commissioning will be tried in IX at beginning. After that, one phase is default.
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- Jig for FC painting: Under manufacturing.
- PF actuator: by the end of January.
VIS Meeting
14:00-16:00
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans