Line 6: Line 6:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15868|15868]], Sunday, VIS/General, '''kouseki.miyo''', Some suspensions are not SAFE.
Line 9: Line 8:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15875|15875]], Monday, VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15885|15885]], Tuesday, VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844)
klog15617
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15872|15872]], Monday, VIS/OMM, '''ryutaro.takahashi''', Comment to Modification of ACCs (Click here to view original report: 15617)
klog15847
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15873|15873]], Monday, VIS/General, '''kouseki.miyo''', Comment to Relay Switch of Stepper Motor Driver (Click here to view original report: 15847)
klog15857
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15876|15876]], Monday, VIS/PR2, '''satoru.ikeda''', Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15880|15880]], Tuesday, VIS/PR2, '''satoru.ikeda''', Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15882|15882]], Tuesday, VIS/PR2, '''satoru.ikeda''', Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
klog15737
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15877|15877]], Monday, VIS/General, '''satoru.ikeda''', Comment to We investigated the network connection. (Click here to view original report: 15737)
klog15878
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15908|15908]], Wednesday, CRY/Cryo-payload EX, '''takafumi.ushiba''', Comment to EX payload upgrade (Click here to view original report: 15878)
klog15889
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15890|15890]], Tuesday, VIS/PR3, '''satoru.ikeda''', Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15911|15911]], Wednesday, VIS/PR3, '''satoru.ikeda''', Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15920|15920]], Wednesday, VIS/PR3, '''satoru.ikeda''', Comment to Traverser motor test and cabling. (Click here to view original report: 15889)

[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15891|15891]], Tuesday, VIS/EY, '''ryutaro.takahashi''', Setup of F3
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15893|15893]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15894|15894]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15906|15906]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15912|15912]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15918|15918]], Wednesday, VIS/EY, '''ryutaro.takahashi''', Comment to Setup of F3 (Click here to view original report: 15891)


[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15868|15868]], Sunday, VIS/General, '''kouseki.miyo''', Some suspensions are not SAFE.
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15923|15923]], Thursday, VIS/General, '''kouseki.miyo''', Comment to Some suspensions are not SAFE. (Click here to view original report: 15868)

klog15905
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15924|15924]], Thursday, PEM/General, '''takaaki.yokozawa''', Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15925|15925]], Thursday, PEM/General, '''shinji.miyoki''', Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15927|15927]], Thursday, PEM/General, '''tatsuki.washimi''', Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15919|15919]], Wednesday, VIS/EY, '''ryutaro.takahashi''', Setup of BF
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15926|15926]], Thursday, VIS/EY, '''kouseki.miyo''', Comment to Setup of BF (Click here to view original report: 15919)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15931|15931]], Thursday, VIS/EY, '''ryutaro.takahashi''', Comment to Setup of BF (Click here to view original report: 15919)


 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15905|15905]], Wednesday, PEM/General, '''tatsuki.washimi''', Bird watching (Ondotori maintenance) 2021
Line 10: Line 49:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15872|15872]], Monday, VIS/OMM, '''ryutaro.takahashi''', Comment to Modification of ACCs (Click here to view original report: 15617)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15873|15873]], Monday, VIS/General, '''kouseki.miyo''', Comment to Relay Switch of Stepper Motor Driver (Click here to view original report: 15847)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15875|15875]], Monday, VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15876|15876]], Monday, VIS/PR2, '''satoru.ikeda''', Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15877|15877]], Monday, VIS/General, '''satoru.ikeda''', Comment to We investigated the network connection. (Click here to view original report: 15737)
Line 16: Line 50:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15880|15880]], Tuesday, VIS/PR2, '''satoru.ikeda''', Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
Line 18: Line 51:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15882|15882]], Tuesday, VIS/PR2, '''satoru.ikeda''', Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
Line 23: Line 55:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15885|15885]], Tuesday, VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844)
Line 25: Line 56:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15890|15890]], Tuesday, VIS/PR3, '''satoru.ikeda''', Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15891|15891]], Tuesday, VIS/EY, '''ryutaro.takahashi''', Setup of F3
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15893|15893]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15894|15894]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15905|15905]], Wednesday, PEM/General, '''tatsuki.washimi''', Bird watching (Ondotori maintenance) 2021
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15906|15906]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15908|15908]], Wednesday, CRY/Cryo-payload EX, '''takafumi.ushiba''', Comment to EX payload upgrade (Click here to view original report: 15878)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15911|15911]], Wednesday, VIS/PR3, '''satoru.ikeda''', Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
Line 34: Line 57:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15912|15912]], Wednesday, VIS/EY, '''kouseki.miyo''', Comment to Setup of F3 (Click here to view original report: 15891)
Line 38: Line 60:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15918|15918]], Wednesday, VIS/EY, '''ryutaro.takahashi''', Comment to Setup of F3 (Click here to view original report: 15891)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15919|15919]], Wednesday, VIS/EY, '''ryutaro.takahashi''', Setup of BF
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15920|15920]], Wednesday, VIS/PR3, '''satoru.ikeda''', Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
Line 42: Line 61:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15923|15923]], Thursday, VIS/General, '''kouseki.miyo''', Comment to Some suspensions are not SAFE. (Click here to view original report: 15868)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15924|15924]], Thursday, PEM/General, '''takaaki.yokozawa''', Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15925|15925]], Thursday, PEM/General, '''shinji.miyoki''', Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15926|15926]], Thursday, VIS/EY, '''kouseki.miyo''', Comment to Setup of BF (Click here to view original report: 15919)
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15927|15927]], Thursday, PEM/General, '''tatsuki.washimi''', Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)
Line 49: Line 63:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15931|15931]], Thursday, VIS/EY, '''ryutaro.takahashi''', Comment to Setup of BF (Click here to view original report: 15919)

Activities in this week

klog15860

  • 15864, Friday, VIS/IX, takafumi.ushiba, Comment to Cabling for cryo-payload (Click here to view original report: 15860)

  • 15866, Friday, VIS/IX, ryutaro.takahashi, Comment to Cabling for cryo-payload (Click here to view original report: 15860)

klog15844

  • 15869, Sunday, VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)

  • 15875, Monday, VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)

  • 15885, Tuesday, VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)

klog15617

  • 15872, Monday, VIS/OMM, ryutaro.takahashi, Comment to Modification of ACCs (Click here to view original report: 15617)

klog15847

  • 15873, Monday, VIS/General, kouseki.miyo, Comment to Relay Switch of Stepper Motor Driver (Click here to view original report: 15847)

klog15857

  • 15876, Monday, VIS/PR2, satoru.ikeda, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)

  • 15880, Tuesday, VIS/PR2, satoru.ikeda, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)

  • 15882, Tuesday, VIS/PR2, satoru.ikeda, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)

klog15737

  • 15877, Monday, VIS/General, satoru.ikeda, Comment to We investigated the network connection. (Click here to view original report: 15737)

klog15878

  • 15908, Wednesday, CRY/Cryo-payload EX, takafumi.ushiba, Comment to EX payload upgrade (Click here to view original report: 15878)

klog15889

  • 15890, Tuesday, VIS/PR3, satoru.ikeda, Comment to Traverser motor test and cabling. (Click here to view original report: 15889)

  • 15911, Wednesday, VIS/PR3, satoru.ikeda, Comment to Traverser motor test and cabling. (Click here to view original report: 15889)

  • 15920, Wednesday, VIS/PR3, satoru.ikeda, Comment to Traverser motor test and cabling. (Click here to view original report: 15889)

15891, Tuesday, VIS/EY, ryutaro.takahashi, Setup of F3

  • 15893, Wednesday, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)

  • 15894, Wednesday, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)

  • 15906, Wednesday, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)

  • 15912, Wednesday, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)

  • 15918, Wednesday, VIS/EY, ryutaro.takahashi, Comment to Setup of F3 (Click here to view original report: 15891)

15868, Sunday, VIS/General, kouseki.miyo, Some suspensions are not SAFE.

  • 15923, Thursday, VIS/General, kouseki.miyo, Comment to Some suspensions are not SAFE. (Click here to view original report: 15868)

klog15905

  • 15924, Thursday, PEM/General, takaaki.yokozawa, Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)

  • 15925, Thursday, PEM/General, shinji.miyoki, Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)

  • 15927, Thursday, PEM/General, tatsuki.washimi, Comment to Bird watching (Ondotori maintenance) 2021 (Click here to view original report: 15905)

15919, Wednesday, VIS/EY, ryutaro.takahashi, Setup of BF

  • 15926, Thursday, VIS/EY, kouseki.miyo, Comment to Setup of BF (Click here to view original report: 15919)

  • 15931, Thursday, VIS/EY, ryutaro.takahashi, Comment to Setup of BF (Click here to view original report: 15919)

  • 15905, Wednesday, PEM/General, tatsuki.washimi, Bird watching (Ondotori maintenance) 2021

  • 15871, Sunday, VIS/General, kouseki.miyo, ISOLATED state is available with only LVDTs not blended sensors.

  • 15878, Monday, CRY/Cryo-payload EX, takafumi.ushiba, EX payload upgrade

  • 15881, Tuesday, PEM/Center, takaaki.yokozawa, IXC

  • 15883, Tuesday, CRY/Cryostat IY, takayuki.tomaru, IYC test (temperature & frosting)

  • 15884, Tuesday, CRY/Cryostat IY, rishabh.bajpai, Vibration Analysis

  • 15886, Tuesday, VIS/PR3, satoru.ikeda, Driveable range of the PR3 GAS SF stepper motor

  • 15888, Tuesday, VIS/General, kouseki.miyo, All payload models are in PAYLOAD_MASTER.mdl

  • 15889, Tuesday, VIS/PR3, fabian.arellano, Traverser motor test and cabling.

  • 15910, Wednesday, VIS/EY, kouseki.miyo, TF measurement for F3 GAS filter

  • 15913, Wednesday, CRY/Cryostat IY, takayuki.tomaru, IYC cooler no.3

  • 15916, Wednesday, IOO/IMC, tomotada.akutsu, Pre-inspection of the suspension structures for MCi

  • 15917, Wednesday, IOO/IMC, tomotada.akutsu, Turned off the power supply to the tilt-sensor laser

  • 15921, Wednesday, VIS/SR3, fabian.arellano, Oplev installation.

  • 15928, Thursday, VIS/SR3, fabian.arellano, Oplev installation and alignment recovery.

  • 15930, Thursday, VIS/PR2, satoru.ikeda, Connect and check the drive of the PR2 traverser.

  • 15932, Thursday, VIS/EY, ryutaro.takahashi, Setup of F3

  • 15933, Thursday, PEM/EY, tatsuki.washimi, portable fluid meter

This text is generated by script in "/kagra/Dropbox/Personal/miyo/Scripts/klog/main.py".

Agenda/Minutes on 2021/2/5

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

Copy from previous meeting

  • Schedule for IX: Connection is scheduled in the week of 2/8. Do you work on 2/11?
  • Schedule for IY: Disconnection is scheduled on 3/11.
  • Schedule for EX: Connection is scheduled in the week of 3/15.
  • Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
  • Commissioning in vacuum: Two phased commissioning will be tried in IX at beginning. After that, one phase is default.
  • Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
  • Jig for FC painting: Under manufacturing.
  • PF actuator: by the end of January.

VIS Meeting

14:00-

Participants:

Progress report

General

Type-A

  • Finished assembly of the ACCs and the geophone pods in IX.
  • Setup the F3: Calibration of the LVDT, Measurement of the FR range, Tuning of filter, Measurement of the TFs, Cabling around the F3.
  • Lifted down the EQ stop into the corrugate tube. The F3 stage sit down the frame lock.

Type-B

Type-Bp

Type-C

  • Remedy of cabling for the actuator coils in the IMC suspensions is required.

Controls

Electronics

Towards O4

Safety

Discussion

Travel Plans

The week from 2/8

  • Takahashi: 2/8-12
  • Sato: 2/8-12
  • Hirata: 2/8-12
  • Yano: 2/8-12

The week from 2/15

  • Takahashi: 2/15-19
  • Sato: 2/15-19
  • Hirata: 2/15-19
  • Yano: 2/15-19

Next meeting

  • On 2020/2/12(Fri)

KAGRA/Subgroups/VIS/VISMinutes20210205 (last edited 2021-02-11 21:23:44 by RyutaroTakahashi)