* Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15860|15860]]: VIS/IX, '''ryutaro.takahashi''', Cabling for cryo-payload * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15859|15859]]: VIS/General, '''shinji.miyoki''', Comment to Temperature during O3GK. (Click here to view original report: 15816) * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15858|15858]]: VIS/PR2, '''kouseki.miyo''', Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857) * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15857|15857]]: VIS/PR2, '''satoru.ikeda''', The PR2-SF's stepper motor has stalled. * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15856|15856]]: VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844) * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15855|15855]]: PEM/General, '''shoichi.oshino''', Replaced wether station PC * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15854|15854]]: VIS/General, '''satoru.ikeda''', Comment to Relay Switch of Stepper Motor Driver (Click here to view original report: 15847) * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15853|15853]]: VIS/SR3, '''fabian.arellano''', Looking for a place for a thermistor around the payload. * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15852|15852]]: VIS/PR3, '''fabian.arellano''', Comment to Gluing the mirror wire. (Click here to view original report: 15844) * Thursday,[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15849|15849]]: CRY/Cryo-payload IX, '''takafumi.ushiba''', Comment to Cabling between BF and PF (Click here to view original report: 15835) |
Agenda/Minutes on 2021/2/5
Activities in this week
Sunday,15871: VIS/General, kouseki.miyo, ISOLATED state is available with only LVDTs not blended sensors.
Sunday,15870: CAL/General, dan.chen, YPcal noise investigation
Sunday,15869: VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)
Sunday,15868: VIS/General, kouseki.miyo, Some suspensions are not SAFE.
Saturday,15867: DGS/General, takahiro.yamamoto, Security update for the gateway server
Friday,15866: VIS/IX, ryutaro.takahashi, Comment to Cabling for cryo-payload (Click here to view original report: 15860)
Friday,15865: DGS/General, takahiro.yamamoto, Installation of a new script server (k1script1)
Friday,15864: VIS/IX, takafumi.ushiba, Comment to Cabling for cryo-payload (Click here to view original report: 15860)
Friday,15863: CAL/General, dan.chen, Safety measures in EYA area
Friday,15862: CAL/General, dan.chen, New storage space for apparatus
CRY+VIS Interface Meeting
13:30-14:00
Participants:
Copy from previous meeting
- Schedule for IX: Connection is scheduled in the week of 2/8.
- Schedule for IY: Disconnection was scheduled on 3/11.
- Schedule for EX: Connection was scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
- Commissioning in vacuum: Two phased commissioning will be tried in IX at beginning. After that, one phase is default.
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- Jig for FC painting: Under manufacturing.
- PF actuator: by the end of January.
VIS Meeting
14:00-16:00
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans