13:30-14:00 Date : 13:30-
Line 10: Line 10:
Participants: Participants : Takahashi, Ikeda, Miyo, Tomaru, Aso, Kimura, Hirata, Sato
Line 13: Line 13:
Line 14: Line 15:
 * IX: Setting Oplev by 3/10. Preparing additional spring for BF.
 * IY: Disconnection is scheduled on 3/11.
 * EX: Connection is scheduled in the week of 3/15.
Line 15: Line 19:
== Status ==
 * Corrugate tube fixing jig: Re-measurement is on going in 2/25-3/2 at IYV.
 * Commissioning in air: Commissioning of IX will be deley.
 * Commissioning in vacuum:
 * Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
 * PF actuator: Not evaluated in IX, but after the commissioning for suspension.
 * Jig for FC painting: Assembling.
 * Overall commissioning: To be considered about personnel.
Line 20: Line 31:
14:00-16:00 14:00-
Line 25: Line 36:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Chart]]
 * Type-A team: IXV in 3/1-3, IMC in 3/4-5
 * Type-B team: EXV in 3/1-2, PR3 in 3/3-5
Line 28: Line 42:
=== TypeA ===
=== TypeB ===
=== TypeBp ===
=== TypeC ===
=== Electronics ===
=== Control ===
Line 32: Line 51:
 * O3GK Noise Budget : Seismic noise through the Type-A tower
  * [[https://gokagra.slack.com/archives/C015M111B5G/p1611978135005400]]
  * Calculation for the ETMY : much smaller than O3GK sensitivity, but larger than the design sensitivity
Line 34: Line 56:
The week from 3/1

 * Takahashi: 3/1-5
 * Sato: 3/1-5
 * Hirata: 3/1-5
 * Yano: 3/1-5

The week from 3/8

 * Takahashi: 3/8-3/12
 * Sato: 3/8-3/12
 * Hirata: 3/8-3/12
 * Yano: 3/8-3/12
Line 35: Line 71:
 * 2021/3/5(FRI)

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date : 13:30-

Participants : Takahashi, Ikeda, Miyo, Tomaru, Aso, Kimura, Hirata, Sato

Post O3 Upgrade portal

Schedule

  • IX: Setting Oplev by 3/10. Preparing additional spring for BF.
  • IY: Disconnection is scheduled on 3/11.
  • EX: Connection is scheduled in the week of 3/15.

Status

  • Corrugate tube fixing jig: Re-measurement is on going in 2/25-3/2 at IYV.
  • Commissioning in air: Commissioning of IX will be deley.
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting: Assembling.
  • Overall commissioning: To be considered about personnel.


VIS Meeting

14:00-

Participants:

Schedule

  • Chart

  • Type-A team: IXV in 3/1-3, IMC in 3/4-5
  • Type-B team: EXV in 3/1-2, PR3 in 3/3-5

Progress report

<< <  2021 / 2 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28

TypeA

TypeB

TypeBp

TypeC

Electronics

Control

Safety

Discussion

Travel Plans

The week from 3/1

  • Takahashi: 3/1-5
  • Sato: 3/1-5
  • Hirata: 3/1-5
  • Yano: 3/1-5

The week from 3/8

  • Takahashi: 3/8-3/12
  • Sato: 3/8-3/12
  • Hirata: 3/8-3/12
  • Yano: 3/8-3/12

Next meeting

  • 2021/3/5(FRI)