Line 8: | Line 8: |
13:30-14:00 | Date : 13:30- |
Line 10: | Line 10: |
Participants: | Participants : Takahashi, Ikeda, Miyo, Tomaru, Aso, Kimura, Hirata, Sato |
Line 13: | Line 13: |
Line 14: | Line 15: |
* IX: Setting Oplev by 3/10. Preparing additional spring for BF. * IY: Disconnection is scheduled on 3/11. * EX: Connection is scheduled in the week of 3/15. |
|
Line 15: | Line 19: |
== Status == * Corrugate tube fixing jig: Started the vent of IYV chamber on 26th. Re-measurement is on going in 2/25-3/2 at IYV. * Commissioning in air: Commissioning of IX will be deley. * Commissioning in vacuum: * Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going. * PF actuator: Not evaluated in IX, but after the commissioning for suspension. * Jig for FC painting: Assembling. * Overall commissioning: To be considered about personnel. |
|
Line 20: | Line 31: |
14:00-16:00 | 14:00- |
Line 25: | Line 36: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Chart]] * Type-A team: IXV in 3/1-3, IMC in 3/4-5 * Type-B team: EXV in 3/1-2, PR3 in 3/3-5 |
|
Line 28: | Line 42: |
=== TypeA === === TypeB === === TypeBp === === TypeC === === Electronics === === Control === |
|
Line 32: | Line 51: |
* O3GK Noise Budget : Seismic noise through the Type-A tower * [[https://gokagra.slack.com/archives/C015M111B5G/p1611978135005400]] * Calculation for the ETMY : much smaller than O3GK sensitivity, but larger than the design sensitivity |
|
Line 34: | Line 56: |
The week from 3/1 * Takahashi: 3/1-5 * Sato: 3/1-5 * Hirata: 3/1-5 * Yano: 3/1-5 The week from 3/8 * Takahashi: 3/8-3/12 * Sato: 3/8-3/12 * Hirata: 3/8-3/12 * Yano: 3/8-3/12 |
|
Line 35: | Line 71: |
* 2021/3/5(FRI) |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants : Takahashi, Ikeda, Miyo, Tomaru, Aso, Kimura, Hirata, Sato
Schedule
- IX: Setting Oplev by 3/10. Preparing additional spring for BF.
- IY: Disconnection is scheduled on 3/11.
- EX: Connection is scheduled in the week of 3/15.
Status
- Corrugate tube fixing jig: Started the vent of IYV chamber on 26th. Re-measurement is on going in 2/25-3/2 at IYV.
- Commissioning in air: Commissioning of IX will be deley.
- Commissioning in vacuum:
- Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting: Assembling.
- Overall commissioning: To be considered about personnel.
VIS Meeting
14:00-
Participants:
Schedule
- Type-A team: IXV in 3/1-3, IMC in 3/4-5
- Type-B team: EXV in 3/1-2, PR3 in 3/3-5
Progress report
<< < 2021 / 2 > >> | ||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
TypeA
TypeB
TypeBp
TypeC
Electronics
Control
Safety
Discussion
- O3GK Noise Budget : Seismic noise through the Type-A tower
https://gokagra.slack.com/archives/C015M111B5G/p1611978135005400
- Calculation for the ETMY : much smaller than O3GK sensitivity, but larger than the design sensitivity
Travel Plans
The week from 3/1
- Takahashi: 3/1-5
- Sato: 3/1-5
- Hirata: 3/1-5
- Yano: 3/1-5
The week from 3/8
- Takahashi: 3/8-3/12
- Sato: 3/8-3/12
- Hirata: 3/8-3/12
- Yano: 3/8-3/12
Next meeting
- 2021/3/5(FRI)