Date : 13:30-13:45 | Date : 13:30- |
Line 15: | Line 15: |
* IX: Setting Oplev by 3/10. Preparing additional spring for BF. * IY: Disconnection is scheduled on 3/11. |
* IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall. * IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11. |
Line 20: | Line 20: |
* Corrugate tube fixing jig: Started the vent of IYV chamber on 26th. Re-measurement is on going in 2/25-3/2 at IYV. * Commissioning in air: Commissioning of IX will be delay. From April? |
* Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV. * Commissioning in air: Commissioning of ITMX is delay. From April? |
Line 25: | Line 25: |
* Jig for FC painting: Assembling. * Overall commissioning: To be considered about personnel. |
* Jig for FC painting: * Overall commissioning: Schedule meeting is requested (after JPS meeting?). |
Line 36: | Line 36: |
14:00-14:30 | 14:00- |
Line 38: | Line 38: |
Participants: Takahashi, Hirata, Miyo, Sato, Fabian, Sugiyama, Ishizaki, Aso, Terrence, Tanaka | Participants: |
Line 41: | Line 41: |
||'''KAGRA'''||'''Suspension-wise''' || '''People-wise''' || || [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt|All schedule]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?action=show&controller=gantts&f%5B%5D=status_id&f%5B%5D=subject&f%5B%5D=&gantt=1&month=3&months=6&op%5Bstatus_id%5D=o&op%5Bsubject%5D=~&project_id=kagra&query%5Bdraw_progress_line%5D=0&query%5Bdraw_relations%5D=1&set_filter=1&utf8=%E2%9C%93&v%5Bsubject%5D%5B%5D=%5BETMX%5D&year=2021&zoom=2|ETMX]] || || || ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?action=show&controller=gantts&f%5B%5D=status_id&f%5B%5D=subject&f%5B%5D=&gantt=1&month=3&months=6&op%5Bstatus_id%5D=o&op%5Bsubject%5D=~&project_id=kagra&query%5Bdraw_progress_line%5D=0&query%5Bdraw_relations%5D=1&set_filter=1&utf8=%E2%9C%93&v%5Bsubject%5D%5B%5D=%5BITMX%5D&year=2021&zoom=2|ITMX]] || || || ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=subject&op%5Bsubject%5D=%7E&v%5Bsubject%5D%5B%5D=%5BETMY%5D&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|ETMY]] || || || ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=subject&op%5Bsubject%5D=%7E&v%5Bsubject%5D%5B%5D=%5BITMY%5D&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|ITMY]] || || |
[[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/Schedule|Schedule]] |
Line 47: | Line 43: |
Suspension schedule ( based on the [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Microsoft project ]]) |
* The next week * Type-A team: 3/9 IXV filter setting, 3/10-11 IYV payload disconnection * Type-B team: 3/9 EXV withdrawal, 3/10-12 PR/SR adjustment |
Line 50: | Line 47: |
* [Miyo] Please check the remaining tasks for PRs and SRs (hardware ) * PR3 * rubbing check * Install OpLev * noise floor check about all sensors: OSEM, OpLev, LVDTs. * Calibration check * PR2 * noise floor check * Install OpLev * Calibration check * PRM * replace the LVDT circuit for BF damper. it is broken. * noise floor check * calibration check * BS * ballast mass adjustment * noise floor check * calibration check * SR3 * ballast mass adjustment * noise floor check * calibration check * SR2 * ballast mass adjustment * Install OpLev * noise floor check * calibration check * SRM * ballast mass adjustment * Install OpLev * noise floor check * calibration check |
|
Line 51: | Line 80: |
* [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=6&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|PRs]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=7&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|BS/SRs]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=10&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Input Optics suspensions]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=20&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Output Optics susspensions]] * People * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=100&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Takahashi]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=107&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Fabian]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=102&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Sato]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=103&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Hirata]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=99&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Ikeda]] * [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=96&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Miyo]] memo * Type-A team: IXV in 3/1-3, IMC in 3/4-5 * Type-B team: EXV in 3/1-2, PR3 in 3/3-5 |
== klog == '''EX''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16084|16084]] Remedy of F0 , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16100|16100]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16116|16116]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16128|16128]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16139|16139]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16159|16159]] Comment , __fabian.arellano__ '''General''' * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16144|16144]] I turned off the electronics in VIS racks in the central room. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16036|16036]] Cabling for temperature control equipment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16114|16114]] Comment , __satoru.ikeda__ '''IX''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16127|16127]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16138|16138]] Comment , __ryutaro.takahashi__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16156|16156]] Comment , __ryutaro.takahashi__ '''IY''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16091|16091]] Monitoring of IP by ITMY venting , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16106|16106]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16107|16107]] Comment , __kouseki.miyo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16115|16115]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16119|16119]] Comment , __satoru.ikeda__ '''MCE''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16101|16101]] Preparation for fixing the MCe coil cable , __naohisa.satou__ '''MCF''' * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16157|16157]] Investigation of IMC suspensions , __ryutaro.takahashi__ '''PR3''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16162|16162]] Comment , __fabian.arellano__ |
Line 70: | Line 114: |
<<MonthCalendar(,2021,3)>> | |
Line 72: | Line 115: |
* Replacement of LVDT coils for F0 in EX. | * Replacement of LVDT coils for F0 was finished in EX. * Tuning of the filter chain is on going in IX. |
Line 77: | Line 121: |
* Investigation and recovery of IMC suspensions are requested. | * Investigation and recovery of the IMC suspensions were performed on 3/4. |
Line 84: | Line 128: |
* O3GK Noise Budget : Seismic noise through the Type-A tower * [[https://gokagra.slack.com/archives/C015M111B5G/p1611978135005400]] * Calculation for the ETMY : much smaller than O3GK sensitivity, but larger than the design sensitivity |
|
Line 89: | Line 130: |
The week from 3/1 * Takahashi: 3/1-5 * Sato: 3/1-5 * Hirata: 3/1-5 * Yano: 3/1-5 |
|
Line 103: | Line 137: |
The week from 3/15 * Takahashi: 3/15-18 * Sato: 3/15-19 * Hirata: 3/15-19 * Yano: 3/15-19 |
|
Line 104: | Line 145: |
* 2021/3/5(FRI) | * 2021/3/12(FRI) |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants :
Schedule
- IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
- IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
- EX: Connection is scheduled in the week of 3/15.
Status
- Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
- Commissioning in air: Commissioning of ITMX is delay. From April?
- Commissioning in vacuum: From May?
- Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning: Schedule meeting is requested (after JPS meeting?).
Discussion
- [Miyo] オフロード作業を無くすためのアイデア募集
- 問題意識:真空圧力が変わるとIPが傾いてPayloadが自身のEQフレームに当たる。(完全に傾かないようにする治具はそもそも不可能なので、傾いても大丈夫なアイデアがほしい。)
[Miyo] そもそも、IPが傾いてIPのEQストップに当たった状態でもPayloadも同じく当たらないよう十分に退避させれば良い話に思える。その場合、IPがEQに当たった状態でFRをつかってもとに戻せるかどうか確認すべき。これはAcceptanceCheckに追加すべきか?
VIS Meeting
14:00-
Participants:
Schedule
* The next week
- Type-A team: 3/9 IXV filter setting, 3/10-11 IYV payload disconnection
- Type-B team: 3/9 EXV withdrawal, 3/10-12 PR/SR adjustment
* [Miyo] Please check the remaining tasks for PRs and SRs (hardware )
- PR3
- PR2
- noise floor check
Install OpLev
- Calibration check
- PRM
- replace the LVDT circuit for BF damper. it is broken.
- noise floor check
- calibration check
- BS
- ballast mass adjustment
- noise floor check
- calibration check
- SR3
- ballast mass adjustment
- noise floor check
- calibration check
- SR2
- ballast mass adjustment
Install OpLev
- noise floor check
- calibration check
- SRM
- ballast mass adjustment
Install OpLev
- noise floor check
- calibration check
klog
EX
16142 IP and F0 stepper motor limit switches. , fabian.arellano
16084 Remedy of F0 , ryutaro.takahashi
16142 IP and F0 stepper motor limit switches. , fabian.arellano
16159 Comment , fabian.arellano
General
16144 I turned off the electronics in VIS racks in the central room. , fabian.arellano
16036 Cabling for temperature control equipment , satoru.ikeda
16114 Comment , satoru.ikeda
IX
16118 Setup of filter chain , ryutaro.takahashi
IY
16091 Monitoring of IP by ITMY venting , satoru.ikeda
16106 Comment , satoru.ikeda
16107 Comment , kouseki.miyo
16115 Comment , satoru.ikeda
16119 Comment , satoru.ikeda
MCE
16101 Preparation for fixing the MCe coil cable , naohisa.satou
MCF
16157 Investigation of IMC suspensions , ryutaro.takahashi
PR3
Progress report
TypeA
- Replacement of LVDT coils for F0 was finished in EX.
- Tuning of the filter chain is on going in IX.
TypeB
TypeBp
TypeC
- Investigation and recovery of the IMC suspensions were performed on 3/4.
Electronics
Control
Safety
Discussion
Travel Plans
The week from 3/8
- Takahashi: 3/8-3/12
- Sato: 3/8-3/12
- Hirata: 3/8-3/12
- Yano: 3/8-3/12
The week from 3/15
- Takahashi: 3/15-18
- Sato: 3/15-19
- Hirata: 3/15-19
- Yano: 3/15-19
Next meeting
- 2021/3/12(FRI)