Date : 13:30-13:45 Date : 13:30-
Line 15: Line 15:
 * IX: Setting Oplev by 3/10. Preparing additional spring for BF.
 * IY: Disconnection is scheduled on 3/11.
 * IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
 * IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
Line 20: Line 20:
 * Corrugate tube fixing jig: Started the vent of IYV chamber on 26th. Re-measurement is on going in 2/25-3/2 at IYV.
 * Commissioning in air: Commissioning of IX will be delay. From April?
 * Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
 * Commissioning in air: Commissioning of ITMX is delay. From April?
Line 25: Line 25:
 * Jig for FC painting: Assembling.
 * Overall commissioning: To be considered about personnel.
 * Jig for FC painting:
 * Overall commissioning: Schedule meeting is requested (after JPS meeting?).
Line 38: Line 38:
Participants: Takahashi, Hirata, Miyo, Sato, Fabian, Sugiyama, Ishizaki, Aso, Terrence, Tanaka Participants:
Line 41: Line 41:
||'''KAGRA'''||'''Suspension-wise''' || '''People-wise''' ||
|| [[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?action=show&controller=gantts&f%5B%5D=status_id&f%5B%5D=parent_id&f%5B%5D=&gantt=1&month=3&months=6&op%5Bparent_id%5D=%21%2A&op%5Bstatus_id%5D=o&project_id=kagra&query%5Bdraw_progress_line%5D=0&query%5Bdraw_relations%5D=1&set_filter=1&utf8=%E2%9C%93&year=2021&zoom=2|All]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?action=show&controller=gantts&f%5B%5D=status_id&f%5B%5D=subject&f%5B%5D=&gantt=1&month=3&months=6&op%5Bstatus_id%5D=o&op%5Bsubject%5D=~&project_id=kagra&query%5Bdraw_progress_line%5D=0&query%5Bdraw_relations%5D=1&set_filter=1&utf8=%E2%9C%93&v%5Bsubject%5D%5B%5D=%5BETMX%5D&year=2021&zoom=2|ETMX]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=100&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Takahashi (Type-A)]] ||
|| ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?action=show&controller=gantts&f%5B%5D=status_id&f%5B%5D=subject&f%5B%5D=&gantt=1&month=3&months=6&op%5Bstatus_id%5D=o&op%5Bsubject%5D=~&project_id=kagra&query%5Bdraw_progress_line%5D=0&query%5Bdraw_relations%5D=1&set_filter=1&utf8=%E2%9C%93&v%5Bsubject%5D%5B%5D=%5BITMX%5D&year=2021&zoom=2|ITMX]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=107&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Fabian (Type-B)]] ||
|| ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=subject&op%5Bsubject%5D=%7E&v%5Bsubject%5D%5B%5D=%5BETMY%5D&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|ETMY]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=102&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Sato]] ||
|| ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=subject&op%5Bsubject%5D=%7E&v%5Bsubject%5D%5B%5D=%5BITMY%5D&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|ITMY]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=103&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Hirata]] ||
|| ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=6&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|PRs]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=99&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Ikeda]] ||
|| ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=7&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|BS/SRs]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=96&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Miyo]] ||
|| ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=10&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Input Optics suspensions]] ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=assigned_to_id&op%5Bassigned_to_id%5D=%3D&v%5Bassigned_to_id%5D%5B%5D=105&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=1&month=3&year=2021&zoom=4|Ushiba(CRY)]] ||
|| ||[[https://dacgit.icrr.u-tokyo.ac.jp/projects/kagra/issues/gantt?utf8=%E2%9C%93&set_filter=1&gantt=1&f%5B%5D=status_id&op%5Bstatus_id%5D=o&f%5B%5D=category_id&op%5Bcategory_id%5D=%3D&v%5Bcategory_id%5D%5B%5D=20&f%5B%5D=&query%5Bdraw_relations%5D=0&query%5Bdraw_relations%5D=1&query%5Bdraw_progress_line%5D=0&months=6&month=3&year=2021&zoom=2|Output Optics susspensions]] || ||
[[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/Schedule|Schedule]]
Line 51: Line 43:
Old? VIS schedule is in [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Microsoft project ]]
  
== klog ==
'''EX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16084|16084]] Remedy of F0 , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16100|16100]] Comment , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16116|16116]] Comment , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16128|16128]] Comment , __fabian.arellano__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16139|16139]] Comment , __fabian.arellano__
'''General'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16036|16036]] Cabling for temperature control equipment , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16114|16114]] Comment , __satoru.ikeda__
'''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16127|16127]] Comment , __ryutaro.takahashi__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16138|16138]] Comment , __ryutaro.takahashi__
'''IY'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16091|16091]] Monitoring of IP by ITMY venting , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16106|16106]] Comment , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16107|16107]] Comment , __kouseki.miyo__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16115|16115]] Comment , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16119|16119]] Comment , __satoru.ikeda__
'''MCE'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16101|16101]] Preparation for fixing the MCe coil cable , __naohisa.satou__

Line 55: Line 70:
 * Replacement of LVDT coils for F0 in EX.  * Replacement of LVDT coils for F0 in EX was finished.
Line 60: Line 75:
 * Investigation and recovery of IMC suspensions are requested.  * Investigation and recovery of the IMC suspensions were performed on 3/4.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date : 13:30-

Participants :

Post O3 Upgrade portal

Schedule

  • IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
  • IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
  • EX: Connection is scheduled in the week of 3/15.

Status

  • Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
  • Commissioning in air: Commissioning of ITMX is delay. From April?
  • Commissioning in vacuum: From May?
  • Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting:
  • Overall commissioning: Schedule meeting is requested (after JPS meeting?).

Discussion

  • [Miyo] オフロード作業を無くすためのアイデア募集
    • 問題意識:真空圧力が変わるとIPが傾いてPayloadが自身のEQフレームに当たる。(完全に傾かないようにする治具はそもそも不可能なので、傾いても大丈夫なアイデアがほしい。)
    • [Miyo] そもそも、IPが傾いてIPのEQストップに当たった状態でもPayloadも同じく当たらないよう十分に退避させれば良い話に思える。その場合、IPがEQに当たった状態でFRをつかってもとに戻せるかどうか確認すべき。これはAcceptanceCheckに追加すべきか?


VIS Meeting

14:00-14:30

Participants:

Schedule

Schedule

klog

EX

  • 16084 Remedy of F0 , ryutaro.takahashi

    • 16100 Comment , ryutaro.takahashi

    • 16116 Comment , fabian.arellano

    • 16128 Comment , fabian.arellano

    • (!) 16139 Comment , fabian.arellano

General

  • 16036 Cabling for temperature control equipment , satoru.ikeda

    • 16114 Comment , satoru.ikeda

IX

  • 16118 Setup of filter chain , ryutaro.takahashi

  • 16118 Setup of filter chain , ryutaro.takahashi

    • 16127 Comment , ryutaro.takahashi

    • (!) 16138 Comment , ryutaro.takahashi

IY

  • 16091 Monitoring of IP by ITMY venting , satoru.ikeda

    • 16106 Comment , satoru.ikeda

    • 16107 Comment , kouseki.miyo

    • 16115 Comment , satoru.ikeda

    • 16119 Comment , satoru.ikeda

MCE

  • 16101 Preparation for fixing the MCe coil cable , naohisa.satou

Progress report

TypeA

  • Replacement of LVDT coils for F0 in EX was finished.

TypeB

TypeBp

TypeC

  • Investigation and recovery of the IMC suspensions were performed on 3/4.

Electronics

Control

Safety

Discussion

Travel Plans

The week from 3/1

  • Takahashi: 3/1-5
  • Sato: 3/1-5
  • Hirata: 3/1-5
  • Yano: 3/1-5

The week from 3/8

  • Takahashi: 3/8-3/12
  • Sato: 3/8-3/12
  • Hirata: 3/8-3/12
  • Yano: 3/8-3/12