4391
Comment:
|
4510
|
Deletions are marked like this. | Additions are marked like this. |
Line 8: | Line 8: |
Date : 13:30-13:45 | Date : 13:30- |
Line 15: | Line 15: |
* IX: Setting Oplev by 3/10. Preparing additional spring for BF. * IY: Disconnection is scheduled on 3/11. * EX: Connection is scheduled in the week of 3/15. |
* IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall. * IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11. * EX: Connection is scheduled in the week of 3/15. Replacement of the LVDT coil for F0 was finished. The limit switches have been installed. |
Line 20: | Line 20: |
* Corrugate tube fixing jig: Started the vent of IYV chamber on 26th. Re-measurement is on going in 2/25-3/2 at IYV. * Commissioning in air: Commissioning of IX will be delay. From April? |
* Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV. * Commissioning in air: Commissioning of IX is delay. From April? |
Line 25: | Line 25: |
* Jig for FC painting: Assembling. * Overall commissioning: To be considered about personnel. |
* Jig for FC painting: * Overall commissioning: Schedule meeting is requested (after JPS meeting?). |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants :
Schedule
- IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
- IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
- EX: Connection is scheduled in the week of 3/15. Replacement of the LVDT coil for F0 was finished. The limit switches have been installed.
Status
- Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
- Commissioning in air: Commissioning of IX is delay. From April?
- Commissioning in vacuum: From May?
- Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning: Schedule meeting is requested (after JPS meeting?).
Discussion
- [Miyo] オフロード作業を無くすためのアイデア募集
- 問題意識:真空圧力が変わるとIPが傾いてPayloadが自身のEQフレームに当たる。(完全に傾かないようにする治具はそもそも不可能なので、傾いても大丈夫なアイデアがほしい。)
[Miyo] そもそも、IPが傾いてIPのEQストップに当たった状態でもPayloadも同じく当たらないよう十分に退避させれば良い話に思える。その場合、IPがEQに当たった状態でFRをつかってもとに戻せるかどうか確認すべき。これはAcceptanceCheckに追加すべきか?
VIS Meeting
14:00-14:30
Participants: Takahashi, Hirata, Miyo, Sato, Fabian, Sugiyama, Ishizaki, Aso, Terrence, Tanaka
Schedule
klog
EX
16084 Remedy of F0 , ryutaro.takahashi
General
IX
IY
16091 Monitoring of IP by ITMY venting , satoru.ikeda
MCE
16101 Preparation for fixing the MCe coil cable , naohisa.satou
Progress report
TypeA
- Replacement of LVDT coils for F0 in EX.
TypeB
TypeBp
TypeC
- Investigation and recovery of IMC suspensions are requested.
Electronics
Control
Safety
Discussion
- O3GK Noise Budget : Seismic noise through the Type-A tower
https://gokagra.slack.com/archives/C015M111B5G/p1611978135005400
- Calculation for the ETMY : much smaller than O3GK sensitivity, but larger than the design sensitivity
Travel Plans
The week from 3/1
- Takahashi: 3/1-5
- Sato: 3/1-5
- Hirata: 3/1-5
- Yano: 3/1-5
The week from 3/8
- Takahashi: 3/8-3/12
- Sato: 3/8-3/12
- Hirata: 3/8-3/12
- Yano: 3/8-3/12
Next meeting
- 2021/3/5(FRI)