Differences between revisions 39 and 40
Revision 39 as of 2021-03-04 08:27:59
Size: 4391
Editor: KousekiMiyo
Comment:
Revision 40 as of 2021-03-04 19:35:35
Size: 4510
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:
Date : 13:30-13:45 Date : 13:30-
Line 15: Line 15:
 * IX: Setting Oplev by 3/10. Preparing additional spring for BF.
 * IY: Disconnection is scheduled on 3/11.
 * EX: Connection is scheduled in the week of 3/15.
 * IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
 * IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
 * EX: Connection is scheduled in the week of 3/15. Replacement of the LVDT coil for F0 was finished. The limit switches have been installed.
Line 20: Line 20:
 * Corrugate tube fixing jig: Started the vent of IYV chamber on 26th. Re-measurement is on going in 2/25-3/2 at IYV.
 * Commissioning in air: Commissioning of IX will be delay. From April?
 * Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
 * Commissioning in air: Commissioning of IX is delay. From April?
Line 25: Line 25:
 * Jig for FC painting: Assembling.
 * Overall commissioning: To be considered about personnel.
 * Jig for FC painting:
 * Overall commissioning: Schedule meeting is requested (after JPS meeting?).

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date : 13:30-

Participants :

Post O3 Upgrade portal

Schedule

  • IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
  • IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
  • EX: Connection is scheduled in the week of 3/15. Replacement of the LVDT coil for F0 was finished. The limit switches have been installed.

Status

  • Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
  • Commissioning in air: Commissioning of IX is delay. From April?
  • Commissioning in vacuum: From May?
  • Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting:
  • Overall commissioning: Schedule meeting is requested (after JPS meeting?).

Discussion

  • [Miyo] オフロード作業を無くすためのアイデア募集
    • 問題意識:真空圧力が変わるとIPが傾いてPayloadが自身のEQフレームに当たる。(完全に傾かないようにする治具はそもそも不可能なので、傾いても大丈夫なアイデアがほしい。)
    • [Miyo] そもそも、IPが傾いてIPのEQストップに当たった状態でもPayloadも同じく当たらないよう十分に退避させれば良い話に思える。その場合、IPがEQに当たった状態でFRをつかってもとに戻せるかどうか確認すべき。これはAcceptanceCheckに追加すべきか?


VIS Meeting

14:00-14:30

Participants: Takahashi, Hirata, Miyo, Sato, Fabian, Sugiyama, Ishizaki, Aso, Terrence, Tanaka

Schedule

Schedule

klog

EX

  • 16084 Remedy of F0 , ryutaro.takahashi

    • 16100 Comment , ryutaro.takahashi

    • 16116 Comment , fabian.arellano

    • 16128 Comment , fabian.arellano

    • (!) 16139 Comment , fabian.arellano

General

  • 16036 Cabling for temperature control equipment , satoru.ikeda

    • 16114 Comment , satoru.ikeda

IX

  • 16118 Setup of filter chain , ryutaro.takahashi

  • 16118 Setup of filter chain , ryutaro.takahashi

    • 16127 Comment , ryutaro.takahashi

    • (!) 16138 Comment , ryutaro.takahashi

IY

  • 16091 Monitoring of IP by ITMY venting , satoru.ikeda

    • 16106 Comment , satoru.ikeda

    • 16107 Comment , kouseki.miyo

    • 16115 Comment , satoru.ikeda

    • 16119 Comment , satoru.ikeda

MCE

  • 16101 Preparation for fixing the MCe coil cable , naohisa.satou

Progress report

TypeA

  • Replacement of LVDT coils for F0 in EX.

TypeB

TypeBp

TypeC

  • Investigation and recovery of IMC suspensions are requested.

Electronics

Control

Safety

Discussion

Travel Plans

The week from 3/1

  • Takahashi: 3/1-5
  • Sato: 3/1-5
  • Hirata: 3/1-5
  • Yano: 3/1-5

The week from 3/8

  • Takahashi: 3/8-3/12
  • Sato: 3/8-3/12
  • Hirata: 3/8-3/12
  • Yano: 3/8-3/12

Next meeting

  • 2021/3/5(FRI)

KAGRA/Subgroups/VIS/VISMinutes20210305 (last edited 2021-03-05 16:43:25 by RyutaroTakahashi)