Line 8: Line 8:
Date : 13:30- Date : 13:30-14:10
Line 21: Line 21:
 * Commissioning in air: Commissioning of ITMX is delay. From April?
 * Commissioning in vacuum: From May?
 * Commissioning in air: Commissioning of ITMX is delay. From June.
 * Commissioning in vacuum:
Line 27: Line 27:
 * Procedure of TM height setting:
Line 36: Line 37:
14:00- 14:10-15:30

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date : 13:30-14:10

Participants : Takahashi, Sato, Ikeda, Ushiba, Kimura, Akutsu, Aso, Hirata, Miyo

Post O3 Upgrade portal

Schedule

  • IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
  • IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
  • EX: Connection is scheduled in the week of 3/15.

Status

  • Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
  • Commissioning in air: Commissioning of ITMX is delay. From June.
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting:
  • Overall commissioning: Schedule meeting is requested (after JPS meeting?).
  • Procedure of TM height setting:

Discussion

  • [Miyo] オフロード作業を無くすためのアイデア募集
    • 問題意識:真空圧力が変わるとIPが傾いてPayloadが自身のEQフレームに当たる。(完全に傾かないようにする治具はそもそも不可能なので、傾いても大丈夫なアイデアがほしい。)
    • [Miyo] そもそも、IPが傾いてIPのEQストップに当たった状態でもPayloadも同じく当たらないよう十分に退避させれば良い話に思える。その場合、IPがEQに当たった状態でFRをつかってもとに戻せるかどうか確認すべき。これはAcceptanceCheckに追加すべきか?


VIS Meeting

14:10-15:30

Participants: Takahashi, Sato, Ikeda, Aso, Hirata, Miyo, Tanaka, Washimi, Sugiyama, Ishizaki, Fabian

Schedule

Schedule

* The next week

  • Type-A team: 3/9 IXV filter setting, 3/10-11 IYV payload disconnection
  • Type-B team: 3/9 EXV withdrawal, 3/10-12 PR/SR adjustment

* [Miyo] Please check the remaining tasks for PRs and SRs (hardware )

  • PR3
    • rubbing check
    • Install OpLev

    • noise floor check about all sensors: OSEM, OpLev, LVDTs.

    • Calibration check
  • PR2
    • noise floor check
    • Install OpLev

    • Calibration check
  • PRM
    • replace the LVDT circuit for BF damper. it is broken.
    • noise floor check
    • calibration check
  • BS
    • ballast mass adjustment
    • noise floor check
    • calibration check
  • SR3
    • ballast mass adjustment
    • noise floor check
    • calibration check
  • SR2
    • ballast mass adjustment
    • Install OpLev

    • noise floor check
    • calibration check
  • SRM
    • ballast mass adjustment
    • Install OpLev

    • noise floor check
    • calibration check

klog

EX

  • 16142 IP and F0 stepper motor limit switches. , fabian.arellano

  • 16084 Remedy of F0 , ryutaro.takahashi

    • 16100 Comment , ryutaro.takahashi

    • 16116 Comment , fabian.arellano

    • 16128 Comment , fabian.arellano

    • 16139 Comment , fabian.arellano

  • 16142 IP and F0 stepper motor limit switches. , fabian.arellano

    • (!) 16159 Comment , fabian.arellano

  • On Monday we removed the jigs from the F0 blades and began adjusting the compression by 2 mm at the time.
  • This work was mostly finished on Wednesday. We gave the jigs to Type-A team in the afternoon. Blades 1, 3, 4 and 5 still require some compression. See this notebook page for details.

  • On Thursday we lowered the keystone and hooked the suspension rod. Then we lifted the keystone until there was some tension in the rod. We didn't proceed with the assembly of the keystone assembly because lifting the load would be required.
  • We installed and tested F0 vertical fishing roid switches. We checked the polarity of the motor also. It was correct.
  • We assembled the F0 yaw stepper motor, tested the limit switches and the polarity. We were all fine. We left the motor on IP table.
  • We took pictures of the IP horizontal fishing rods for Ikeda-san.

General

  • (!) 16144 I turned off the electronics in VIS racks in the central room. , fabian.arellano

  • 16036 Cabling for temperature control equipment , satoru.ikeda

    • 16114 Comment , satoru.ikeda

  • On Monday We have to set the appropriate setting of the signal generators for PR, BS and SR suspensions.

IX

  • 16118 Setup of filter chain , ryutaro.takahashi

    • 16127 Comment , ryutaro.takahashi

    • 16138 Comment , ryutaro.takahashi

    • (!) 16156 Comment , ryutaro.takahashi

IY

  • 16091 Monitoring of IP by ITMY venting , satoru.ikeda

  • 16106 Comment , satoru.ikeda

  • 16107 Comment , kouseki.miyo

  • 16115 Comment , satoru.ikeda

  • 16119 Comment , satoru.ikeda

MCE

  • 16101 Preparation for fixing the MCe coil cable , naohisa.satou

MCF

  • (!) 16157 Investigation of IMC suspensions , ryutaro.takahashi

PR3

  • 15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda

    • (!) 16162 Comment , fabian.arellano

In PR3 we inspected the OSEM flags with the optic fibre camera. They all seem to be in place.

Progress report

TypeA

  • Replacement of LVDT coils for F0 was finished in EX.
  • Tuning of the filter chain is on going in IX.

TypeB

TypeBp

TypeC

  • Investigation and recovery of the IMC suspensions were performed on 3/4.

Electronics

Control

Safety

Discussion

Travel Plans

The week from 3/8

  • Takahashi: 3/8-3/12
  • Sato: 3/8-3/12
  • Hirata: 3/8-3/12
  • Yano: 3/8-3/12

The week from 3/15

  • Takahashi: 3/15-18
  • Sato: 3/15-19
  • Hirata: 3/15-19
  • Yano: 3/15-19

Next meeting

  • 2021/3/12(FRI)