Size: 7242
Comment:
|
Size: 5632
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 49: | Line 49: |
* [Miyo] Please check the remaining tasks for PRs and SRs (hardware ) | == klog == |
Line 51: | Line 51: |
* PR3 * rubbing check * Install OpLev * noise floor check about all sensors: OSEM, OpLev, LVDTs. * Calibration check * PR2 * noise floor check * Install OpLev * Calibration check * PRM * replace the LVDT circuit for BF damper. it is broken. * noise floor check * calibration check * BS * ballast mass adjustment * noise floor check * calibration check * SR3 * ballast mass adjustment * noise floor check * calibration check * SR2 * ballast mass adjustment * Install OpLev * noise floor check * calibration check * SRM * ballast mass adjustment * Install OpLev * noise floor check * calibration check |
'''EX''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16183|16183]] Cleaning and transportation of components. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16170|16170]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16178|16178]] Comment , __fabian.arellano__ '''General''' * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16200|16200]] Recovery of the signal generators in Type-B and Type-Bp suspensions. , __fabian.arellano__ '''IX''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16185|16185]] Added MN/PF OpLev to k1visitmxp's Model file. , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16199|16199]] Setup of IP , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16171|16171]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16195|16195]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16185|16185]] Added MN/PF OpLev to k1visitmxp's Model file. , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16197|16197]] Comment , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16216|16216]] Comment , __satoru.ikeda__ '''IY''' * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16214|16214]] Preparation for disconnection of cryo-payload , __ryutaro.takahashi__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16217|16217]] Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , __satoru.ikeda__ '''MCF''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16157|16157]] Investigation of IMC suspensions , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16180|16180]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16181|16181]] Comment , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16182|16182]] Comment , __shinji.miyoki__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16198|16198]] Comment , __kouseki.miyo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16201|16201]] Comment , __tomotada.akutsu__ '''PR3''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16204|16204]] Comment , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16207|16207]] Comment , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16223|16223]] Comment , __fabian.arellano__ |
Line 83: | Line 83: |
== klog == '''EX''' |
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py. |
Line 86: | Line 85: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16084|16084]] Remedy of F0 , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16100|16100]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16116|16116]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16128|16128]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16139|16139]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16159|16159]] Comment , __fabian.arellano__ * On Monday we removed the jigs from the F0 blades and began adjusting the compression by 2 mm at the time. * This work was mostly finished on Wednesday. We gave the jigs to Type-A team in the afternoon. Blades 1, 3, 4 and 5 still require some compression. See [[https://photos.app.goo.gl/nzXUoTYVzXdZVLir7|this notebook page for details]]. * On Thursday we lowered the keystone and hooked the suspension rod. Then we lifted the keystone until there was some tension in the rod. We didn't proceed with the assembly of the keystone assembly because lifting the load would be required. * We installed and tested F0 vertical fishing roid switches. We checked the polarity of the motor also. It was correct. * We assembled the F0 yaw stepper motor, tested the limit switches and the polarity. We were all fine. We left the motor on IP table. * We took pictures of the IP horizontal fishing rods for Ikeda-san. '''General''' * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16144|16144]] I turned off the electronics in VIS racks in the central room. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16036|16036]] Cabling for temperature control equipment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16114|16114]] Comment , __satoru.ikeda__ * On Monday We have to set the appropriate setting of the signal generators for PR, BS and SR suspensions. '''IX''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16127|16127]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16138|16138]] Comment , __ryutaro.takahashi__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16156|16156]] Comment , __ryutaro.takahashi__ '''IY''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16091|16091]] Monitoring of IP by ITMY venting , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16106|16106]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16107|16107]] Comment , __kouseki.miyo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16115|16115]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16119|16119]] Comment , __satoru.ikeda__ '''MCE''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16101|16101]] Preparation for fixing the MCe coil cable , __naohisa.satou__ '''MCF''' * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16157|16157]] Investigation of IMC suspensions , __ryutaro.takahashi__ '''PR3''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16162|16162]] Comment , __fabian.arellano__ In PR3 we inspected the OSEM flags with the optic fibre camera. They all seem to be in place. == Progress report == |
== Summary Report == |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-14:10
Participants : Takahashi, Sato, Ikeda, Ushiba, Kimura, Akutsu, Aso, Hirata, Miyo
Schedule
- IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
- IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
- EX: Connection is scheduled in the week of 3/15.
Status
- Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
- Commissioning in air: Commissioning of ITMX is delay. From June.
- Commissioning in vacuum:
- Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning: Schedule meeting is requested (after JPS meeting?).
- Procedure of TM height setting:
Discussion
- [Miyo] オフロード作業を無くすためのアイデア募集
- 問題意識:真空圧力が変わるとIPが傾いてPayloadが自身のEQフレームに当たる。(完全に傾かないようにする治具はそもそも不可能なので、傾いても大丈夫なアイデアがほしい。)
[Miyo] そもそも、IPが傾いてIPのEQストップに当たった状態でもPayloadも同じく当たらないよう十分に退避させれば良い話に思える。その場合、IPがEQに当たった状態でFRをつかってもとに戻せるかどうか確認すべき。これはAcceptanceCheckに追加すべきか?
VIS Meeting
14:10-15:30
Participants: Takahashi, Sato, Ikeda, Aso, Hirata, Miyo, Tanaka, Washimi, Sugiyama, Ishizaki, Fabian
Schedule
* The next week
- Type-A team: 3/9 IXV filter setting, 3/10-11 IYV payload disconnection
- Type-B team: 3/9 EXV withdrawal, 3/10-12 PR/SR adjustment
klog
EX
16183 Cleaning and transportation of components. , fabian.arellano
16142 IP and F0 stepper motor limit switches. , fabian.arellano
General
16200 Recovery of the signal generators in Type-B and Type-Bp suspensions. , fabian.arellano
IX
16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda
16199 Setup of IP , ryutaro.takahashi
16118 Setup of filter chain , ryutaro.takahashi
16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda
IY
16214 Preparation for disconnection of cryo-payload , ryutaro.takahashi
16217 Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , satoru.ikeda
MCF
16157 Investigation of IMC suspensions , ryutaro.takahashi
PR3
15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
TypeA
- Replacement of LVDT coils for F0 was finished in EX.
- Tuning of the filter chain is on going in IX.
TypeB
TypeBp
TypeC
- Investigation and recovery of the IMC suspensions were performed on 3/4.
Electronics
Control
Safety
Discussion
Travel Plans
The week from 3/8
- Takahashi: 3/8-3/12
- Sato: 3/8-3/12
- Hirata: 3/8-3/12
- Yano: 3/8-3/12
The week from 3/15
- Takahashi: 3/15-18
- Sato: 3/15-19
- Hirata: 3/15-19
- Yano: 3/15-19
Next meeting
- 2021/3/12(FRI)