Size: 6720
Comment:
|
Size: 9134
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 10: | Line 10: |
Participants : | Participants : Takahashi, Ikeda, Ohashi, Kimura, Aso, Hirata, Sato, Ushiba, Tomaru, Akutsu, Miyo |
Line 15: | Line 15: |
* IX: Oplev setting by 3/10. F0 and IP were tuned. | * IX: Oplev setting will be carried out after the next week. F0 and IP were tuned. Yaw will be adjusted after rough alignment. |
Line 18: | Line 18: |
* EY: Cryo-payload was removed on 3/12. Cable treatment is necessary. | |
Line 20: | Line 21: |
* Corrugate tube fixing jig: * Commissioning in air: From June for IX? |
* Corrugate tube fixing jig: The spacer is modified. They should be prepared by mid. May. * Commissioning in air: From mid. May for IX. |
Line 26: | Line 27: |
* Overall commissioning: Schedule meeting after JPS meeting. | * Overall commissioning: Schedule meeting on 3/22. |
Line 35: | Line 36: |
Participants: | Participants: Takahashi, Fabian, Hirata, Miyo, Tanaka, Sato, Washimi, Terrence, Aso |
Line 43: | Line 44: |
* Type-B team: 3/15-19 remedy of IY or still PR3 setting. | * Type-B team: 3/15-19 PR3 setting. Remedy work of IY will be postponed. |
Line 47: | Line 48: |
Line 49: | Line 49: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__ | * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__ |
Line 52: | Line 52: |
Line 54: | Line 53: |
* (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16200|16200]] Recovery of the signal generators in Type-B and Type-Bp suspensions. , __fabian.arellano__ |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16200|16200]] Recovery of the signal generators in Type-B and Type-Bp suspensions. , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16234|16234]] Common Type-C(MCI,MCE,MCO,IMMT1,IMMT2) model. , __satoru.ikeda__ |
Line 58: | Line 56: |
Line 61: | Line 58: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__ | * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__ |
Line 64: | Line 61: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16185|16185]] Added MN/PF OpLev to k1visitmxp's Model file. , __satoru.ikeda__ | * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16185|16185]] Added MN/PF OpLev to k1visitmxp's Model file. , __satoru.ikeda__ |
Line 66: | Line 63: |
* (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16216|16216]] Comment , __satoru.ikeda__ |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16216|16216]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16199|16199]] Setup of IP , __ryutaro.takahashi__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16238|16238]] Comment , __ryutaro.takahashi__ |
Line 69: | Line 67: |
* (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16214|16214]] Preparation for disconnection of cryo-payload , __ryutaro.takahashi__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16217|16217]] Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , __satoru.ikeda__ |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16214|16214]] Preparation for disconnection of cryo-payload , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16217|16217]] Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16249|16249]] Connection of release sensors to DGS , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16091|16091]] Monitoring of IP by ITMY venting , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16248|16248]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16214|16214]] Preparation for disconnection of cryo-payload , __ryutaro.takahashi__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16237|16237]] Comment , __ryutaro.takahashi__ |
Line 74: | Line 75: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16157|16157]] Investigation of IMC suspensions , __ryutaro.takahashi__ |
* (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16242|16242]] MCi and MCo oplev TX replacing , __tomotada.akutsu__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16157|16157]] Investigation of IMC suspensions , __ryutaro.takahashi__ |
Line 81: | Line 82: |
* (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16225|16225]] Comment , __kouseki.miyo__ |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16225|16225]] Comment , __kouseki.miyo__ |
Line 84: | Line 84: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16204|16204]] Comment , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16207|16207]] Comment , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16223|16223]] Comment , __fabian.arellano__ |
* (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16239|16239]] Test of PR3 mirror pitch stability using the Donald Trump method. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16204|16204]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16207|16207]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16223|16223]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16228|16228]] Comment , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16239|16239]] Test of PR3 mirror pitch stability using the Donald Trump method. , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16247|16247]] Comment , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16246|16246]] Comment , __fabian.arellano__ |
Line 120: | Line 124: |
* [Miyo] We have to resolve the picomotor range probblem before closing MCE and MCF chambers. * [Miyo] We will start the suspension commissioning work including the oplev calibration in next week. |
|
Line 124: | Line 131: |
* [Ikeda] Add new RTM block of additional MN and PF OpLevs of Cryo-payload in the current RTM. * [Ikeda] ITMY is updated with new RTM. * [Ikeda] Now, the old RTM used in O3 is only installed on BS and PR3. Please see [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/RealTimeModel#RTM_Status|Wiki]] |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants : Takahashi, Ikeda, Ohashi, Kimura, Aso, Hirata, Sato, Ushiba, Tomaru, Akutsu, Miyo
Schedule
- IX: Oplev setting will be carried out after the next week. F0 and IP were tuned. Yaw will be adjusted after rough alignment.
- IY: Cryo-payload was removed on 3/11.
- EX: Connection is scheduled in the next week.
- EY: Cryo-payload was removed on 3/12. Cable treatment is necessary.
Status
- Corrugate tube fixing jig: The spacer is modified. They should be prepared by mid. May.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning: Schedule meeting on 3/22.
- Procedure of TM height setting:
Discussion
VIS Meeting
14:00-
Participants: Takahashi, Fabian, Hirata, Miyo, Tanaka, Sato, Washimi, Terrence, Aso
Schedule
* The next week
- Type-A team: 3/15-16 connection of cryo-payload in EX. 3/17- go back to EY
- Type-B team: 3/15-19 PR3 setting. Remedy work of IY will be postponed.
klog
EX
16183 Cleaning and transportation of components. , fabian.arellano
16142 IP and F0 stepper motor limit switches. , fabian.arellano
General
16200 Recovery of the signal generators in Type-B and Type-Bp suspensions. , fabian.arellano
16234 Common Type-C(MCI,MCE,MCO,IMMT1,IMMT2) model. , satoru.ikeda
IX
16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda
16199 Setup of IP , ryutaro.takahashi
16118 Setup of filter chain , ryutaro.takahashi
16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda
16199 Setup of IP , ryutaro.takahashi
16238 Comment , ryutaro.takahashi
IY
16214 Preparation for disconnection of cryo-payload , ryutaro.takahashi
16217 Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , satoru.ikeda
16249 Connection of release sensors to DGS , ryutaro.takahashi
16091 Monitoring of IP by ITMY venting , satoru.ikeda
16248 Comment , satoru.ikeda
16214 Preparation for disconnection of cryo-payload , ryutaro.takahashi
16237 Comment , ryutaro.takahashi
MCF
16242 MCi and MCo oplev TX replacing , tomotada.akutsu
16157 Investigation of IMC suspensions , ryutaro.takahashi
PR3
16239 Test of PR3 mirror pitch stability using the Donald Trump method. , fabian.arellano
15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda
16239 Test of PR3 mirror pitch stability using the Donald Trump method. , fabian.arellano
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
TypeA
- Disconnected the cryo-payload in IY.
- Setup the F0 and tuned the IP in IX.
TypeB
TypeBp
PR3
- At the begining of the week the IM was still touching the IRM.
- First we did a health check of the IM-Y picomotor because I had the impression it had reached a limit.
- We locked the BF and pushed the IRM in yaw such that the IM was hanging free.
- We actuated in yaw using the picomotor and it moved freely suggesting it had not reached its limit.
- With confidence in the picomotor condition we proceeded to adjust yaw and pitch until the IM became free although the OSEM flags were not at the centres of their cavities.
- Measurements of IM TFs revealed the system was healthy. (IM-V TF was not measured because the SF is locked due to the plastic cover.)
Happily, we can consider the system to be recovered from the jammed-BF-picomotor-earthqueake event.
- Later we moved the IM picomotors in order to move the OSEM flags closer to centers of their cavities.However, this rendered H3 out of range.
- The locked theIRM and the IM and moved H3 into range, but when we released the system we realized V1 had become out of range due to a change in pitch.
- We measured transfer functions with the horizontal OSEMs and they were all good.
- We proceeded with the Trump method to test the pitch stability:
We carried out the procedure from the control room and used the readout from V2 and V3 (V1 out of range) and the 3D-CAD to calculate the change in pitch: -3.9 mrad (consistent with what was measured with an oplev when we disturbed the suspension when we glued the wire).
In the tunnel we carried out the procedure again and used an oplev to measure a change of 33.4 mrad. See the videos.
For the same event we used the V2 and V3 OSEMs to estimate the change in pitch of the IM: 4.1 mrad (consistent with previous measurements).
- Today we inspected the payload visually.
- We didn't find anything wrong.
- Only H2 flag rotated during the Trump procedure. See pictures.
TypeC
- [Miyo] We have to resolve the picomotor range probblem before closing MCE and MCF chambers.
- [Miyo] We will start the suspension commissioning work including the oplev calibration in next week.
Electronics
- [Takahashi] Connected the release sensors to the DGS using the exchange cables in IY.
Control
[Ikeda] Add new RTM block of additional MN and PF OpLevs of Cryo-payload in the current RTM.
- [Ikeda] ITMY is updated with new RTM.
[Ikeda] Now, the old RTM used in O3 is only installed on BS and PR3. Please see Wiki
Safety
Discussion
Travel Plans
The week from 3/15
- Takahashi: 3/15-18
- Sato: 3/15-19
- Hirata: 3/15-19
- Yano: 3/15-19
The week from 3/22
- Takahashi: 3/22-3/26
- Sato: 3/22-3/26
- Hirata: 3/22-3/26
- Yano: 3/22-3/26
Next meeting
- 2021/3/19(FRI)