Line 49: Line 49:
* [Miyo] Please check the remaining tasks for PRs and SRs (hardware ) == klog ==
*
  * '''EX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16183|16183]] Cleaning and transportation of components. , __fabian.arellano__
 * '''EX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16142|16142]] IP and F0 stepper motor limit switches. , __fabian.arellano__
  * '''EX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16170|16170]] Comment , __satoru.ikeda__
  * '''EX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16178|16178]] Comment , __fabian.arellano__
 *
  * '''General'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16200|16200]] Recovery of the signal generators in Type-B and Type-Bp suspensions. , __fabian.arellano__
  * '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16185|16185]] Added MN/PF OpLev to k1visitmxp's Model file. , __satoru.ikeda__
  * '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16199|16199]] Setup of IP , __ryutaro.takahashi__
 * '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16118|16118]] Setup of filter chain , __ryutaro.takahashi__
  * '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16171|16171]] Comment , __ryutaro.takahashi__
  * '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16195|16195]] Comment , __ryutaro.takahashi__
 * '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16185|16185]] Added MN/PF OpLev to k1visitmxp's Model file. , __satoru.ikeda__
  * '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16197|16197]] Comment , __satoru.ikeda__
  * '''IX'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16216|16216]] Comment , __satoru.ikeda__
 *
  * '''IY'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16214|16214]] Preparation for disconnection of cryo-payload , __ryutaro.takahashi__
  * '''IY'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16217|16217]] Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , __satoru.ikeda__
 * '''MCF'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16157|16157]] Investigation of IMC suspensions , __ryutaro.takahashi__
  * '''MCF'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16180|16180]] Comment , __ryutaro.takahashi__
  * '''MCF'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16181|16181]] Comment , __takaaki.yokozawa__
  * '''MCF'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16182|16182]] Comment , __shinji.miyoki__
  * '''MCF'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16198|16198]] Comment , __kouseki.miyo__
  * '''MCF'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16201|16201]] Comment , __tomotada.akutsu__
 * '''PR3'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__
  * '''PR3'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16204|16204]] Comment , __fabian.arellano__
  * '''PR3'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16207|16207]] Comment , __fabian.arellano__
  * '''PR3'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16223|16223]] Comment , __fabian.arellano__
Line 51: Line 104:
 * PR3
  * rubbing check
  * Install OpLev
  * noise floor check about all sensors: OSEM, OpLev, LVDTs.
  * Calibration check
 * PR2
  * noise floor check
  * Install OpLev
  * Calibration check
 * PRM
  * replace the LVDT circuit for BF damper. it is broken.
  * noise floor check
  * calibration check
 * BS
  * ballast mass adjustment
  * noise floor check
  * calibration check
 * SR3
  * ballast mass adjustment
  * noise floor check
  * calibration check
 * SR2
  * ballast mass adjustment
  * Install OpLev
  * noise floor check
  * calibration check
 * SRM
  * ballast mass adjustment
  * Install OpLev
  * noise floor check
  * calibration check
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.*
Line 83: Line 106:
== klog ==
Line 87: Line 109:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16170|16170]] Comment , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16178|16178]] Comment , __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16170|16170]] Comment , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16178|16178]] Comment , __fabian.arellano__
'''General'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16200|16200]] Recovery of the signal generators in Type-B and Type-Bp suspensions. , __fabian.arellano__
Line 90: Line 114:
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16199|16199]] Setup of IP , __ryutaro.takahashi__  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16185|16185]] Added MN/PF OpLev to k1visitmxp's Model file. , __satoru.ikeda__
 *
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16199|16199]] Setup of IP ,  __ryutaro.takahashi__
Line 92: Line 117:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16171|16171]] Comment , __ryutaro.takahashi__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16195|16195]] Comment , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16171|16171]] Comment , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16195|16195]] Comment ,  __ryutaro.takahashi__
Line 95: Line 120:
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16197|16197]] Comment , __satoru.ikeda__  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16197|16197]] Comment , __satoru.ikeda__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16216|16216]] Comment , __satoru.ikeda__
'''IY'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16214|16214]] Preparation for disconnection of cryo-payload , __ryutaro.takahashi__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16217|16217]] Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , __satoru.ikeda__
Line 98: Line 127:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16180|16180]] Comment , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16181|16181]] Comment , __takaaki.yokozawa__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16182|16182]] Comment , __shinji.miyoki__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16198|16198]] Comment , __kouseki.miyo__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16201|16201]] Comment , __tomotada.akutsu__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16180|16180]] Comment , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16181|16181]] Comment , __takaaki.yokozawa__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16182|16182]] Comment , __shinji.miyoki__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16198|16198]] Comment , __kouseki.miyo__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16201|16201]] Comment , __tomotada.akutsu__
'''PR3'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__
* (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16204|16204]] Comment , __fabian.arellano__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16207|16207]] Comment , __fabian.arellano__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16223|16223]] Comment , __fabian.arellano__
Line 105: Line 139:

== Progress report ==
== Progress Summary==

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date : 13:30-14:10

Participants : Takahashi, Sato, Ikeda, Ushiba, Kimura, Akutsu, Aso, Hirata, Miyo

Post O3 Upgrade portal

Schedule

  • IX: Oplev setting will be finished by 3/10. Mystery of 5-kg overload. The ballast on the F0 is too tall.
  • IY: The vent was finished on 3/2. Disconnection is scheduled on 3/11.
  • EX: Connection is scheduled in the week of 3/15.

Status

  • Corrugate tube fixing jig: Re-measurement was performed in 2/25-3/2 at IYV.
  • Commissioning in air: Commissioning of ITMX is delay. From June.
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting:
  • Overall commissioning: Schedule meeting is requested (after JPS meeting?).
  • Procedure of TM height setting:

Discussion

  • [Miyo] オフロード作業を無くすためのアイデア募集
    • 問題意識:真空圧力が変わるとIPが傾いてPayloadが自身のEQフレームに当たる。(完全に傾かないようにする治具はそもそも不可能なので、傾いても大丈夫なアイデアがほしい。)
    • [Miyo] そもそも、IPが傾いてIPのEQストップに当たった状態でもPayloadも同じく当たらないよう十分に退避させれば良い話に思える。その場合、IPがEQに当たった状態でFRをつかってもとに戻せるかどうか確認すべき。これはAcceptanceCheckに追加すべきか?


VIS Meeting

14:10-15:30

Participants: Takahashi, Sato, Ikeda, Aso, Hirata, Miyo, Tanaka, Washimi, Sugiyama, Ishizaki, Fabian

Schedule

Schedule

* The next week

  • Type-A team: 3/9 IXV filter setting, 3/10-11 IYV payload disconnection
  • Type-B team: 3/9 EXV withdrawal, 3/10-12 PR/SR adjustment

klog

*

  • EX

  • 16183 Cleaning and transportation of components. , fabian.arellano

  • EX

  • 16142 IP and F0 stepper motor limit switches. , fabian.arellano

    • EX

  • 16170 Comment , satoru.ikeda

    • EX

  • 16178 Comment , fabian.arellano

    • General

  • (!) 16200 Recovery of the signal generators in Type-B and Type-Bp suspensions. , fabian.arellano

    • IX

  • 16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda

    • IX

  • 16199 Setup of IP , ryutaro.takahashi

  • IX

  • 16118 Setup of filter chain , ryutaro.takahashi

    • IX

  • 16171 Comment , ryutaro.takahashi

    • IX

  • 16195 Comment , ryutaro.takahashi

  • IX

  • 16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda

    • IX

  • 16197 Comment , satoru.ikeda

    • IX

  • (!) 16216 Comment , satoru.ikeda

    • IY

  • (!) 16214 Preparation for disconnection of cryo-payload , ryutaro.takahashi

    • IY

  • (!) 16217 Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , satoru.ikeda

  • MCF

  • 16157 Investigation of IMC suspensions , ryutaro.takahashi

    • MCF

  • 16180 Comment , ryutaro.takahashi

    • MCF

  • 16181 Comment , takaaki.yokozawa

    • MCF

  • 16182 Comment , shinji.miyoki

    • MCF

  • 16198 Comment , kouseki.miyo

    • MCF

  • 16201 Comment , tomotada.akutsu

  • PR3

  • 15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda

    • PR3

  • (!) 16204 Comment , fabian.arellano

    • PR3

  • (!) 16207 Comment , fabian.arellano

    • PR3

  • (!) 16223 Comment , fabian.arellano

This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.*

EX

  • 16183 Cleaning and transportation of components. , fabian.arellano

  • 16142 IP and F0 stepper motor limit switches. , fabian.arellano

  • 16170 Comment , satoru.ikeda

  • 16178 Comment , fabian.arellano

General

  • (!) 16200 Recovery of the signal generators in Type-B and Type-Bp suspensions. , fabian.arellano

IX

  • 16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda

  • 16199 Setup of IP , ryutaro.takahashi

  • 16118 Setup of filter chain , ryutaro.takahashi

  • 16171 Comment , ryutaro.takahashi

  • 16195 Comment , ryutaro.takahashi

  • 16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda

  • 16197 Comment , satoru.ikeda

  • (!) 16216 Comment , satoru.ikeda

IY

  • (!) 16214 Preparation for disconnection of cryo-payload , ryutaro.takahashi

  • (!) 16217 Support for common Payload/Tower model files: Type-A (ITMY) is supported to TOWER_MASTER/PAYLOAD_MASTER. , satoru.ikeda

MCF

  • 16157 Investigation of IMC suspensions , ryutaro.takahashi

  • 16180 Comment , ryutaro.takahashi

  • 16181 Comment , takaaki.yokozawa

  • 16182 Comment , shinji.miyoki

  • 16198 Comment , kouseki.miyo

  • 16201 Comment , tomotada.akutsu

PR3

  • 15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda

  • (!) 16204 Comment , fabian.arellano

  • (!) 16207 Comment , fabian.arellano

  • (!) 16223 Comment , fabian.arellano

This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py. == Progress Summary==

TypeA

  • Replacement of LVDT coils for F0 was finished in EX.
  • Tuning of the filter chain is on going in IX.

TypeB

TypeBp

TypeC

  • Investigation and recovery of the IMC suspensions were performed on 3/4.

Electronics

Control

Safety

Discussion

Travel Plans

The week from 3/8

  • Takahashi: 3/8-3/12
  • Sato: 3/8-3/12
  • Hirata: 3/8-3/12
  • Yano: 3/8-3/12

The week from 3/15

  • Takahashi: 3/15-18
  • Sato: 3/15-19
  • Hirata: 3/15-19
  • Yano: 3/15-19

Next meeting

  • 2021/3/12(FRI)

KAGRA/Subgroups/VIS/VISMinutes20210312 (last edited 2021-03-12 15:19:04 by RyutaroTakahashi)