Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date : 13:30-

Participants : Post O3 Upgrade portal

Schedule

  • IX: Oplev setting will be carried out in the next week. Yaw will be adjusted after rough alignment.
  • IY:
  • EX: Cryo-payload was installed. Release is scheduled on 3/22.
  • EY: Installation of the F1 stage was started.

Status

  • Corrugate tube fixing jig: They will be prepared by the end of May.
  • Commissioning in air: From mid. May for IX.
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX/EX and Type-A tower in EY/IX are on going.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting:
  • Overall commissioning: Schedule meeting on 3/22.
  • Procedure of TM height setting:

Discussion


VIS Meeting

14:00-

Participants:

Schedule

Schedule

* The next week

  • Type-A team: 3/22-26 installation in EY. 3/23 F0 tuning in EX.
  • Type-B team: 3/22-26 Remedy in PR3.

Klog

EX

  • 16260 Connection of cryo-payload , ryutaro.takahashi

    • 16271 Comment , ryutaro.takahashi

    • 16275 Comment , ryutaro.takahashi

EY

  • 16276 Setup of F1 , ryutaro.takahashi

    • (!) 16288 Comment , ryutaro.takahashi

General

  • 16234 Common Type-C(MCI,MCE,MCO,IMMT1,IMMT2) model. , satoru.ikeda

    • 16261 Comment , satoru.ikeda

    • 16269 Comment , satoru.ikeda

  • 16252 Common Type-C(OMMT1,OMMT2,OSTM) model. , satoru.ikeda

    • 16262 Comment , satoru.ikeda

    • 16268 Comment , satoru.ikeda

IX

  • 16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda

    • 16278 Comment , satoru.ikeda

IY

  • 16249 Connection of release sensors to DGS , ryutaro.takahashi

  • 16091 Monitoring of IP by ITMY venting , satoru.ikeda

    • 16248 Comment , satoru.ikeda

  • 16249 Connection of release sensors to DGS , ryutaro.takahashi

    • 16251 Comment , naohisa.satou

MCF

  • 16242 MCi and MCo oplev TX replacing , tomotada.akutsu

  • 16279 IMC oplev characterization and MCe oplev TX replacing , tomotada.akutsu

  • 16157 Investigation of IMC suspensions , ryutaro.takahashi

    • (!) 16286 Comment , kouseki.miyo

PR3

  • 16258 Setting the alignment of PR3. , fabian.arellano

  • (!) 16287 Comparison of PR3 and SR3 wire clamps. , fabian.arellano

  • 16239 Test of PR3 mirror pitch stability using the Donald Trump method. , fabian.arellano

    • 16247 Comment , fabian.arellano

    • 16246 Comment , fabian.arellano

  • 16272 Tightening of the wire clamp screws. , fabian.arellano

    • 16277 Comment , fabian.arellano

This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.

Summary Report

TypeA

  • Connected the cryo-payload to the BF in EX. The load for BF was roughly adjusted. The F1, F3, BF are working. The F0 overloads by 13kg.
  • Started the setup of F1 in EY.

TypeB

TypeBp

PR3

Given the fact that the gluing of the wire underneath the mirror didn't fix the problem of the stability of the mirror, we decided to tighten the wire clamps.

  • We locked the payload.
  • Removed H1 and H2 OSEM flsags with long and narrow pliers.
  • Removed the side panels.
  • Tighetened the screws of the weight-holding wires to 10 Nm
  • Tighetened the screws of the RM locating wire screws to 2 Nm. They rotated beytween 45 degrees and 95 degrees. (The screw hards for the mirror wires are not accesible).
  • After reassembly we tested pitch stabiliry with the Trupm procedure.
    • The mirror pitch changed by -5.8 mrad (oplev).
    • The IM pitch changed by 1. 04 mrad (V2 and V3 OSEMs).
  • Given this result we want to apply adhesive to the wires at the bottom of the clamps: see slides.

TypeC

Electronics

Control

Safety

Discussion

Travel Plans

The week from 3/22

  • Takahashi: 3/22-3/26
  • Sato: 3/22-3/26
  • Hirata: 3/22-3/26
  • Yano: 3/22-3/26

The week from 3/29

  • Takahashi: 3/29-4/2
  • Sato: 3/29-4/2
  • Hirata: 3/29-4/2
  • Yano: 3/29-4/2

Next meeting

  • 2021/3/26(FRI)