Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants :
Schedule
- IX: Oplev will be finalized in April.
- IY:
- EX: Oplev setting is on going. The payload was released?
- EY: Installation of the F1 stage was almost finished. Countermeasure for the contamination is scheduled on 4/5-6.
Status
- Corrugate tube fixing jig: They will be prepared by the end of May.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Check items for in-air commissioning should be confirmed on the payload. Review of each stage in Type-A tower is necessary.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning: Schedule meeting was held on 3/22.
- Procedure of TM height setting:
Discussion
VIS Meeting
14:00-
Participants:
Schedule
* The next week
- Type-A team: 3/30-31 ACC in IX. 4/1-2 F0 tuning in EX.
- Type-B team: 3/29-4/2 Remedy in PR3.
Klog
EX
16260 Connection of cryo-payload , ryutaro.takahashi
EY
General
16234 Common Type-C(MCI,MCE,MCO,IMMT1,IMMT2) model. , satoru.ikeda
16252 Common Type-C(OMMT1,OMMT2,OSTM) model. , satoru.ikeda
IX
IY
16249 Connection of release sensors to DGS , ryutaro.takahashi
16091 Monitoring of IP by ITMY venting , satoru.ikeda
16248 Comment , satoru.ikeda
16249 Connection of release sensors to DGS , ryutaro.takahashi
16251 Comment , naohisa.satou
MCF
16242 MCi and MCo oplev TX replacing , tomotada.akutsu
16279 IMC oplev characterization and MCe oplev TX replacing , tomotada.akutsu
16157 Investigation of IMC suspensions , ryutaro.takahashi
16286 Comment , kouseki.miyo
PR3
16258 Setting the alignment of PR3. , fabian.arellano
16287 Comparison of PR3 and SR3 wire clamps. , fabian.arellano
16239 Test of PR3 mirror pitch stability using the Donald Trump method. , fabian.arellano
16272 Tightening of the wire clamp screws. , fabian.arellano
16277 Comment , fabian.arellano
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
TypeA
TypeB
TypeBp
TypeC
Electronics
Control
Safety
Discussion
Travel Plans
The week from 3/29
- Takahashi: 3/29-4/2
- Sato: 3/29-4/2
- Hirata: 3/29-4/2
- Yano: 3/29-31
The week from 4/5
- Takahashi: 4/5-9
- Sato: 4/5-9
- Hirata: 4/5-9
Next meeting
- 2021/4/2(FRI)