Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date : 13:30-

Participants :

Post O3 Upgrade portal

Schedule

  • IX: Oplev will be finalized in April. ACC installation will be started in April.
  • IY:
  • EX: Oplev setting is on going. The payload has been released?
  • EY: Installation of the F1 stage was almost finished. Countermeasure for the contamination is scheduled on 4/5-6.

Status

  • Corrugate tube fixing jig: They will be prepared by the end of May.
  • Commissioning in air: From mid. May for IX.
  • Commissioning in vacuum:
  • Acceptance check: Check items for in-air commissioning should be confirmed on the payload. Review of each stage in Type-A tower is necessary.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting:
  • Overall commissioning: Schedule meeting was held on 3/22.
  • Procedure of TM height setting:

Discussion


VIS Meeting

14:00-

Participants:

Schedule

Schedule

* The next week

  • Type-A team: 3/30-31 ACC in IX. 4/1-2 F0 tuning in EX.
  • Type-B team: 3/29-4/2 Remedy in PR3.

Klog

EX

  • 16260 Connection of cryo-payload , ryutaro.takahashi

    • 16271 Comment , ryutaro.takahashi

    • 16275 Comment , ryutaro.takahashi

EY

  • 16276 Setup of F1 , ryutaro.takahashi

    • (!) 16288 Comment , ryutaro.takahashi

General

  • 16234 Common Type-C(MCI,MCE,MCO,IMMT1,IMMT2) model. , satoru.ikeda

    • 16261 Comment , satoru.ikeda

    • 16269 Comment , satoru.ikeda

  • 16252 Common Type-C(OMMT1,OMMT2,OSTM) model. , satoru.ikeda

    • 16262 Comment , satoru.ikeda

    • 16268 Comment , satoru.ikeda

IX

  • 16185 Added MN/PF OpLev to k1visitmxp's Model file. , satoru.ikeda

    • 16278 Comment , satoru.ikeda

IY

  • 16249 Connection of release sensors to DGS , ryutaro.takahashi

  • 16091 Monitoring of IP by ITMY venting , satoru.ikeda

    • 16248 Comment , satoru.ikeda

  • 16249 Connection of release sensors to DGS , ryutaro.takahashi

    • 16251 Comment , naohisa.satou

MCF

  • 16242 MCi and MCo oplev TX replacing , tomotada.akutsu

  • 16279 IMC oplev characterization and MCe oplev TX replacing , tomotada.akutsu

  • 16157 Investigation of IMC suspensions , ryutaro.takahashi

    • (!) 16286 Comment , kouseki.miyo

PR3

  • 16258 Setting the alignment of PR3. , fabian.arellano

  • (!) 16287 Comparison of PR3 and SR3 wire clamps. , fabian.arellano

  • 16239 Test of PR3 mirror pitch stability using the Donald Trump method. , fabian.arellano

    • 16247 Comment , fabian.arellano

    • 16246 Comment , fabian.arellano

  • 16272 Tightening of the wire clamp screws. , fabian.arellano

    • 16277 Comment , fabian.arellano

This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.

Summary Report

TypeA

TypeB

TypeBp

TypeC

Electronics

Control

Safety

Discussion

Travel Plans

The week from 3/29

  • Takahashi: 3/29-4/2
  • Sato: 3/29-4/2
  • Hirata: 3/29-4/2
  • Yano: 3/29-31

The week from 4/5

  • Takahashi: 4/5-9
  • Sato: 4/5-9
  • Hirata: 4/5-9

Next meeting

  • 2021/4/2(FRI)

KAGRA/Subgroups/VIS/VISMinutes20210326 (last edited 2021-03-26 15:09:12 by RyutaroTakahashi)