Date : 13:30-14:15 | Date : 13:30- |
Line 10: | Line 10: |
Participants : Takahashi, Aso, Ikeda, Tomaru, Ushiba, Sato, Miyo | Participants : |
Line 17: | Line 17: |
* EX: Oplev setting is on going. The payload has been released? * EY: Installation of the F1 stage was almost finished. Countermeasure for the contamination is scheduled on 4/5-6. Removing of the maraging rod is necessary. |
* EX: Oplev setting is on going. Payload was released on 4/1. F0 tuning is on going. * EY: Installation of the tower will be restarted in May. Countermeasure for the contamination is scheduled on 4/5-6. Removing of the maraging rod is necessary. |
Line 24: | Line 24: |
* Acceptance check: Check items for in-air commissioning should be confirmed on the payload. Present status of EYV was shown. | * Acceptance check: Check items for in-air commissioning should be confirmed on the payload. |
Line 27: | Line 27: |
* Overall commissioning: Schedule meeting was held on 3/22. | * Overall commissioning: |
Line 34: | Line 34: |
14:15-15:00 | 14:00- |
Line 36: | Line 36: |
Participants: Takahashi, Fabian, Aso, Hirata, Miyo, Ishizaki, Tanaka, Sato, Sugiyama | Participants: |
Line 73: | Line 73: |
EY cabling * According to the continuity check at F1, disconnection of the LVDT (actuator coil) of BF was found, but we have not been able to determine where the break occurred. |
|
Line 78: | Line 74: |
=== TypeBp PR3 === This week we did two tasks, both related with PR3 clamps: * We measured the gaps in PR3 locating clamps for the 200 um piano wire and * We tested applying adhesive to the wires within the grooves in the locating clamps. * One magnet from the IM OSEM flags was chipped. We need to get another one. See [[https://photos.app.goo.gl/3cu5TECSb8hXkkW56|this picture]]. Size of gaps * We used thickness gauges. * We measured the gaps in different places to take into account that the gaps are not necessarily uniform. * The largest gap size was between 170 um and 180 um. * The lowest one was between 70 um and 80 um. * The tickness of the clamped wire is 200 um. Gluing test. * Using a spare SR style clamp we tested the procedure. Let's see klog [[https://klog.icrr.u-tokyo.ac.jp//?r=16331|16331]] and [[https://klog.icrr.u-tokyo.ac.jp//?r=16338|16338]] for details. * The test was successful in the sense that the adhesive went into the gap and the grooves around the wires. However, I wonder if this tiny amount of glue would keep the wires in place. Is there another option before deciding to hang the mirror again? Yes * During the gluing test we saw that the outer locating clamps was not badly scared, neither the tungsten wire. See pictures. * In order to access the screws of the inner locating clamps to tighten them we could do something like this: * Lock the payload, remove the IRM side panels (already done). * Remove the coils from the back ring of the RM in ordet to protect the magnet standoffs. * Release the mirror from the RM and withdraw the lower screws by more than a few milimeters. * Lift the RM by 3 mm using the screws from the security structure. * Loosen the outer locating clamps and move the wires out of the way just enough for the tool to reach the inner screw. * Tighten the inner screws with 2 Nm torque. * Put the tungsten wires back in the grooves and tighten the clamp again. * Lower the RM * Etc. * Washimi-san and I can do preparation on Monday and on Tuesday we can tighten the screws with Hirata-san. |
=== TypeBp === |
Line 119: | Line 81: |
The week from 3/29 * Takahashi: 3/29-4/2 * Sato: 3/29-4/2 * Hirata: 3/29-4/2 * Yano: 3/29-31 |
|
Line 128: | Line 83: |
* Takahashi: 4/5-9 | * Takahashi: 4/5-8 |
Line 132: | Line 87: |
The week from 4/12 * Takahashi: 4/12-16 * Sato: 4/12-16 * Hirata: 4/12-16 |
|
Line 133: | Line 94: |
* 2021/4/2(FRI) | * 2021/4/9(FRI) |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants :
Schedule
- IX: Oplev will be finalized in April. ACC installation will be started in April.
- IY:
- EX: Oplev setting is on going. Payload was released on 4/1. F0 tuning is on going.
- EY: Installation of the tower will be restarted in May. Countermeasure for the contamination is scheduled on 4/5-6. Removing of the maraging rod is necessary.
Status
- Corrugate tube fixing jig: They will be prepared by the end of May.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Check items for in-air commissioning should be confirmed on the payload.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning:
- Procedure of TM height setting: More information on the range and limit is necessary to decide procedure. Prepare for the measurement in the first in-vacuum commissioning in IX.
Discussion
VIS Meeting
14:00-
Participants:
Schedule
See Schedule
Milestone
IMC suspensions are ready in air [40] will finish 2011/04/21.
PRs are ready in air [643] will finish 2011/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2011/11/24.
SRs are ready in air [663] will finish 2011/12/20.
Output suspensions are ready in air [695] will finish 2011/12/21.
TMSY is ready in air [708] will finish 2011/??/??.
TMSX is ready in air [684] will finish 2011/??/??.
2021/03/29
Klog
EY
16276 Setup of F1 , ryutaro.takahashi
16336 Comment , naohisa.satou
16353 Comment , ryutaro.takahashi
General
16349 Some of the EPICS channels have been changed to science frames , satoru.ikeda
16356 Added EPICS channel for , satoru.ikeda
PR3
16310 Preparation for testing the procedure to glue the piano wire at the locating clamps in the IM. , fabian.arellano
16338 Comment , fabian.arellano
16348 Tightening the locating clamps for the piano wire. , fabian.arellano
16355 Comment , fabian.arellano
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
TypeA
TypeB
TypeBp
TypeC
Electronics
Control
Safety
Discussion
Travel Plans
The week from 4/5
- Takahashi: 4/5-8
- Sato: 4/5-9
- Hirata: 4/5-9
The week from 4/12
- Takahashi: 4/12-16
- Sato: 4/12-16
- Hirata: 4/12-16
Next meeting
- 2021/4/9(FRI)