Date : 13:30-14:30 | Date : 13:30- |
Line 10: | Line 10: |
Participants : Takahashi, Hirata, Sato, Aso, Ushiba, Ikeda, Miyo, Akutsu, Kimura, Tomaru | Participants : |
Line 15: | Line 15: |
* IX: Oplev will be finalized in April. Height and alignment adjustments are planed on 4/7-8. ACC will be installed in April. | * IX: Oplev will be finalized in April. Height and alignment adjustments are on going. ACC will be installed in April. |
Line 17: | Line 17: |
* EX: Oplev setting is on going. Payload was released on 4/1. F0 was tuned. * EY: Installation of the tower will be restarted in May. Countermeasure for the contamination is scheduled on 4/5-6. Removing of the maraging rod is necessary. |
* EX: Oplev setting is on going. * EY: Installation of the tower will be restarted in May. Removing of the maraging rod is necessary. |
Line 25: | Line 25: |
* PF actuator: Not evaluated in IX, but after the commissioning for suspension. | * PF actuator: After the commissioning for suspension. |
Line 28: | Line 28: |
* Procedure of TM height setting: More information on the range and limit is necessary to decide procedure. Prepare for the measurement in the first in-vacuum commissioning in IX. | * Procedure of TM height setting: Prepare for the measurement in the first in-vacuum commissioning in IX. |
Line 33: | Line 33: |
14:30-15:10 | 14:30- |
Line 35: | Line 35: |
Participants: Takahashi, Fabian, Tanaka, Sugiyama, Terrence,Aso, Hirata, Sato, Miyo | Participants: |
Line 40: | Line 40: |
* Type-A team: MCo 4/6, IXV 4/7-8 * Type-B team: PR3 4/5-9 |
* Type-A team: IXV 4/13-16 * Type-B team: PR2 4/13-16 |
Line 80: | Line 80: |
I will explain using [[https://1drv.ms/b/s!AoQaV1tdsEcUgeNmg0hHZMMSejqOdA?e=AI19Xb|this short presentation]] about the adjustment of PR3 inner wire locating clamps. |
|
Line 88: | Line 86: |
The week from 4/5 * Takahashi: 4/5-8 * Sato: 4/5-9 * Hirata: 4/5-9 |
|
Line 100: | Line 92: |
The week from 4/19 * Takahashi: 4/19-23 * Sato: 4/19-23 * Hirata: 4/19-23 |
|
Line 101: | Line 99: |
* 2021/4/9(FRI) | * 2021/4/16(FRI) |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants :
Schedule
- IX: Oplev will be finalized in April. Height and alignment adjustments are on going. ACC will be installed in April.
- IY: Remedy of the pre-isolator is scheduled in April.
- EX: Oplev setting is on going.
- EY: Installation of the tower will be restarted in May. Removing of the maraging rod is necessary.
Status
- Corrugate tube fixing jig: They will be prepared by the end of May.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Check items for in-air commissioning should be confirmed on the payload.
- PF actuator: After the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning:
- Procedure of TM height setting: Prepare for the measurement in the first in-vacuum commissioning in IX.
Discussion
VIS Meeting
14:30-
Participants:
Schedule
See Schedule
- Type-A team: IXV 4/13-16
- Type-B team: PR2 4/13-16
Milestone
IMC suspensions are ready in air [40] will finish 2011/04/21.
PRs are ready in air [643] will finish 2011/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2011/11/24.
SRs are ready in air [663] will finish 2011/12/20.
Output suspensions are ready in air [695] will finish 2011/12/21.
TMSY is ready in air [708] will finish 2011/??/??.
TMSX is ready in air [684] will finish 2011/??/??.
2021/03/29
Klog
EX
General
16383 Fixed that ACC and VEL of Picomotor Ch1 was different from other Ch2 to 4. , satoru.ikeda
16391 Supported for common Payload model files: Type-Bp(PR3) to PAYLOAD_MASTER , satoru.ikeda
16402 Change the name of EPICS channel in MASTERSWITCH , satoru.ikeda
16391 Supported for common Payload model files: Type-Bp(PR3) to PAYLOAD_MASTER , satoru.ikeda
16401 Comment , satoru.ikeda
MCF
16405 Unable to connect Picomotor in MCO , satoru.ikeda
PR2
16406 Inspection of locating wire inner clamps , fabian.arellano
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
TypeA
TypeB
TypeBp
TypeC
Electronics
Control
Safety
Discussion
Travel Plans
The week from 4/12
- Takahashi: 4/12-16
- Sato: 4/12-16
- Hirata: 4/12-16
The week from 4/19
- Takahashi: 4/19-23
- Sato: 4/19-23
- Hirata: 4/19-23
Next meeting
- 2021/4/16(FRI)