Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:30-
Participants :
Schedule
- IX: Oplev will be finalized in April. Height and alignment adjustments are on going. ACC will be installed in April.
- Height adjustment of the pre-isolator with pistons.
- IY: Remedy of the pre-isolator will be postponed.
- EX: Height and alignment adjustments are scheduled in 4/20-23.
- EY: Installation of the tower will be restarted in May. Removing of the maraging rod is necessary.
Status
- Corrugate tube fixing jig: They will be prepared by the end of May.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Check items for in-air commissioning should be confirmed on the payload.
- PF actuator: After the commissioning for suspension.
- Jig for FC painting:
- Overall commissioning:
- Procedure of TM height setting: Prepare for the measurement in the first in-vacuum commissioning in IX.
Discussion
VIS Meeting
14:30-
Participants:
Schedule
See Schedule
- Type-A team: EXV 4/20-23
- Type-B team: Remain work on Type-B/Bp.
Milestone
IMC suspensions are ready in air [40] will finish 2011/04/21.
PRs are ready in air [643] will finish 2011/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2011/11/24.
SRs are ready in air [663] will finish 2011/12/20.
Output suspensions are ready in air [695] will finish 2011/12/21.
TMSY is ready in air [708] will finish 2011/??/??.
TMSX is ready in air [684] will finish 2011/??/??.
2021/03/29 updated
Klog
BS
16447 Support for common Tower/Payload model files: Type-B(BS) supports TOWER_MASTER and PAYLOAD_MASTER. , satoru.ikeda
General
16446 Model files have been modified. , satoru.ikeda
16445 Buoyancy effect in PR suspensions. , fabian.arellano
16465 Laser level deviation from the horizontal. , fabian.arellano
16465 Laser level deviation from the horizontal. , fabian.arellano
16466 Comment , tomotada.akutsu
IX
16468 Tuning of LVDT type accelerometer for ITMX , kouseki.miyo
16365 Wiring the release sensor (outside the vacuum chamber) , naohisa.satou
16438 Comment , naohisa.satou
16421 Height adjustment of ITMX , ryutaro.takahashi
MCF
16463 Taking picture of MCo coils , takaaki.yokozawa
PR2
16417 Tightening of the inner wire locating clamps. , fabian.arellano
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
TypeA
TypeB
Type-Bp
TypeC
Electronics
Control
Safety
Discussion
Travel Plans
The week from 4/19
- Takahashi: 4/19-23
- Sato: 4/19-23
- Hirata: 4/19-23
The week from 4/26
- Takahashi: 4/26-28
- Sato: 4/26-5/1
- Hirata: 4/26-28
Next meeting
- 2021/4/23(FRI)