Line 15: | Line 15: |
* IX: Oplev setting is on going. Final setting of height was scheduled on 4/26. ACC tuning is scheduled on 4/24. | * IX: Oplev setting is on going. Final setting of height was applied on 4/26. One ACC was tuned on 4/24. |
Line 17: | Line 17: |
* EX: Height adjustment is on going ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16535|Measurement]]). Rough setting was scheduled on 4/27. * EY: Installation of the tower will be restarted in May. Removing of the maraging rod is necessary. |
* EX: Height adjustment is on going ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16613|Status]]). * EY: Installation of the tower will be restarted on 5/11. Removing of the maraging rod is necessary. |
Line 21: | Line 21: |
* Corrugate tube fixing jig: Implementation for IXV is scheduled on 4/28. | * Corrugate tube fixing jig: Replaced for IXV on 4/28. |
Line 27: | Line 27: |
* Overall commissioning: Schedule meeting was held on 4/19. * Procedure of TM height setting: Plan for IX/EX. |
* Overall commissioning: * Procedure of TM height setting: Plan for EX. |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date : 13:00-
Participants:
Schedule
- IX: Oplev setting is on going. Final setting of height was applied on 4/26. One ACC was tuned on 4/24.
- IY: Remedy of the pre-isolator was postponed.
EX: Height adjustment is on going (Status).
- EY: Installation of the tower will be restarted on 5/11. Removing of the maraging rod is necessary.
Status
- Corrugate tube fixing jig: Replaced for IXV on 4/28.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Meeting (workshop) was set every Friday to make the acceptance check document.
- PF actuator: After SC.
- Jig for FC painting:
- Overall commissioning:
- Procedure of TM height setting: Plan for EX.
Discussion
VIS Meeting
14:00-
Participants:
Schedule
See Schedule
- Type-A team: IXV 5/10, EYV 5/11-13
- Type-B team:
Milestone
IMC suspensions are ready in air [40] will finish 2011/04/21.
PRs are ready in air [643] will finish 2011/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2011/11/24.
SRs are ready in air [663] will finish 2011/12/20.
Output suspensions are ready in air [695] will finish 2011/12/21.
TMSY is ready in air [708] will finish 2011/??/??.
TMSX is ready in air [684] will finish 2011/??/??.
2021/03/29 updated
Klog
EX
16535 Height adjustment of ETMX , ryutaro.takahashi
General
16506 Deleted unnecessary processes from VIS model file. , satoru.ikeda
IX
16421 Height adjustment of ITMX , ryutaro.takahashi
MCE
16512 MCe oplev characterization , takaaki.yokozawa
MCF
16498 Type-C simulation model , yoichi.aso
16501 Oplev calibration MCo , takaaki.yokozawa
16500 Characterization of optical lever MCi , takaaki.yokozawa
16537 MCo suspension strange , tomotada.akutsu
16157 Investigation of IMC suspensions , ryutaro.takahashi
16513 Comment , kouseki.miyo
PR3
16520 Thermistor installation , fabian.arellano
16521 Setting the mirror to nominal height , fabian.arellano
16348 Tightening the locating clamps for the piano wire. , fabian.arellano
16502 Comment , fabian.arellano
16520 Thermistor installation , fabian.arellano
16533 Comment , fabian.arellano
16521 Setting the mirror to nominal height , fabian.arellano
PRM
SR2
16509 Lowering the pre-isolator , fabian.arellano
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
TypeA
TypeB
Type-Bp
TypeC
Electronics
Control
Safety
Discussion
Travel Plans
The week from 5/3
- Hirata: 5/6-9
The week from 5/10
- Takahashi: 5/10-14
- Sato: 5/10-14
- Hirata: 5/10-14
- Yano: 5/10-14
Next meeting
- 2021/5/14(FRI)