Line 21: Line 21:
 * Corrugate tube fixing jig: Replaced for IXV on 4/28. Other 3 sets are necessary by late July.  * Corrugate tube fixing jig: Replaced for IXV. Other 3 sets are necessary by late July.
 * Procedure of TM height setting: Plan for EX.
Line 26: Line 27:
 * Jig for FC painting:
 * Overall commissioning:
 * Procedure of TM height setting: Plan for EX.
 * Jig for FC painting: Test was scheduled in the week of 5/17.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date 2021/5/7: 13:00-

Participants:

Post O3 Upgrade portal

Schedule

  • IX: IP will be released on 5/10. To adjust the length Oplev, it is necessary to damp the filter chain.
  • IY: Remedy of the pre-isolator was postponed.
  • EX: Height adjustment is on going (Status). The measured height of ETMX (-19.5mm) is too low.

  • EY: Installation of the tower will be restarted on 5/11. Removing of the maraging rod is necessary.

Status

  • Corrugate tube fixing jig: Replaced for IXV. Other 3 sets are necessary by late July.
  • Procedure of TM height setting: Plan for EX.
  • Commissioning in air: From mid. May for IX.
  • Commissioning in vacuum:
  • Acceptance check: Group work is set every Friday to make the acceptance check document.
  • PF actuator: After SC.
  • Jig for FC painting: Test was scheduled in the week of 5/17.

Discussion