Date 2021/5/7: 13:00- | Date: 2021/5/7 13:00- |
Line 10: | Line 10: |
Participants: | Participants: Takahashi, Miyo, Tomaru, Aso, Ikeda, Ushiba, Node, Akutsu, Kimura, Hirata |
Line 15: | Line 15: |
* IX: IP will be released on 5/10. To adjust the length Oplev, it is necessary to damp the filter chain. * IY: Remedy of the pre-isolator was postponed. * EX: Height adjustment is on going ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16613|Status]]). The measured height of ETMX (-19.5mm) is too low. * EY: Installation of the tower will be restarted on 5/11. Removing of the maraging rod is necessary. |
* IX: IP will be released on 5/10. To adjust the length Oplev, damping of the filter chain is necessary. * IY: Remedy of the pre-isolator is postponed. * EX: Height adjustment is on going ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16644|Status]]). * EY: Installation of the tower will be restarted on 5/11. Removing of the maraging rod is necessary. Items (pure water maker, etc.) for the mirror cleaning will be ready in 2 weeks. |
Line 21: | Line 21: |
* Corrugate tube fixing jig: Replaced for IXV on 4/28. Other 3 sets are necessary by late July. | * Corrugate tube fixing jig: Replaced for IXV. Other 3 sets are necessary by late July. * TM height setting: Final setting of height in EX was scheduled on 5/12. Angle adjustment in EX was scheduled on 5/13. |
Line 26: | Line 27: |
* Jig for FC painting: * Overall commissioning: * Procedure of TM height setting: Plan for EX. |
* Jig for FC painting: Test was scheduled in the week of 5/17. Minimum target is to learn the procedure with the jig. |
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/5/7 13:00-
Participants: Takahashi, Miyo, Tomaru, Aso, Ikeda, Ushiba, Node, Akutsu, Kimura, Hirata
Schedule
- IX: IP will be released on 5/10. To adjust the length Oplev, damping of the filter chain is necessary.
- IY: Remedy of the pre-isolator is postponed.
EX: Height adjustment is on going (Status).
- EY: Installation of the tower will be restarted on 5/11. Removing of the maraging rod is necessary. Items (pure water maker, etc.) for the mirror cleaning will be ready in 2 weeks.
Status
- Corrugate tube fixing jig: Replaced for IXV. Other 3 sets are necessary by late July.
- TM height setting: Final setting of height in EX was scheduled on 5/12. Angle adjustment in EX was scheduled on 5/13.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Group work is set every Friday to make the acceptance check document.
- PF actuator: After SC.
- Jig for FC painting: Test was scheduled in the week of 5/17. Minimum target is to learn the procedure with the jig.