Differences between revisions 3 and 4
Revision 3 as of 2021-05-14 14:30:46
Size: 7318
Comment:
Revision 4 as of 2021-05-14 14:37:40
Size: 7335
Comment:
Deletions are marked like this. Additions are marked like this.
Line 156: Line 156:
 * Aso: 5/17-20

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2021/5/14 13:00-

Participants:

Post O3 Upgrade portal

Schedule

  • IX: IP was released on 5/10. Adjustment of Yaw FR is scheduled on 5/17.
  • IY: Remedy of the pre-isolator is postponed.
  • EX: Height adjustment was finished (Status).

  • EY: Installation of the tower was restarted on 5/11. The maraging rod was removed. Items (pure water maker, etc.) for the mirror cleaning are under preparation.

Status

  • Corrugate tube fixing jig: Other 3 sets will be ready by the end of June.
  • TM height setting: Final setting of height in EX was on 5/13. Angle adjustment in EX was scheduled on 5/13.
  • Commissioning in air: Started on the pre-isolator in IX.
  • Commissioning in vacuum:
  • Overall commissioning: Operators are necessary.
  • Acceptance check: Group work is set every Friday to make the acceptance check document.
  • PF actuator: After SC.
  • Jig for FC painting: Test is scheduled in the week of 5/17. Minimum target is to learn the procedure with the jig.

Discussion


VIS Meeting

14:00-

Participants:

Schedule

See Schedule

  • Type-A team: IXV 5/17, EYV 5/18-21
  • Type-B team: FC painting test 5/17-19, MSB?

Milestone

  • IMC suspensions are ready in air [40] will finish 2011/04/21.

  • PRs are ready in air [643] will finish 2011/07/09.

  • ETMX is ready in air [656] will finish 2021/08/25.

  • ITMX is ready in air [657] will finish 2021/08/31.

  • ETMY is ready in air [658] will finish 2021/09/16.

  • ITMY is ready in air [659] will finish 2021/11/08.

  • BS is ready in air [691] will finish 2011/11/24.

  • SRs are ready in air [663] will finish 2011/12/20.

  • Output suspensions are ready in air [695] will finish 2011/12/21.

  • TMSY is ready in air [708] will finish 2011/??/??.

  • TMSX is ready in air [684] will finish 2011/??/??.

2021/03/29 updated

Klog

EX

  • (!) 16535 Height adjustment of ETMX , ryutaro.takahashi

General

  • 16506 Deleted unnecessary processes from VIS model file. , satoru.ikeda

IX

  • 16421 Height adjustment of ITMX , ryutaro.takahashi

    • 16499 Comment , ryutaro.takahashi

    • 16519 Comment , ryutaro.takahashi

MCE

  • 16512 MCe oplev characterization , takaaki.yokozawa

    • 16525 Comment , takaaki.yokozawa

    • (!) 16522 Comment , tomotada.akutsu

MCF

  • 16498 Type-C simulation model , yoichi.aso

  • 16501 Oplev calibration MCo , takaaki.yokozawa

  • 16500 Characterization of optical lever MCi , takaaki.yokozawa

  • (!) 16537 MCo suspension strange , tomotada.akutsu

  • 16157 Investigation of IMC suspensions , ryutaro.takahashi

    • 16513 Comment , kouseki.miyo

PR3

  • 16520 Thermistor installation , fabian.arellano

  • 16521 Setting the mirror to nominal height , fabian.arellano

  • 16348 Tightening the locating clamps for the piano wire. , fabian.arellano

    • 16502 Comment , fabian.arellano

  • 16520 Thermistor installation , fabian.arellano

    • (!) 16533 Comment , fabian.arellano

  • 16521 Setting the mirror to nominal height , fabian.arellano

    • (!) 16532 Comment , shinji.miyoki

    • (!) 16529 Comment , fabian.arellano

PRM

  • 16518 PRM BF-LVDT replacement , yoichi.aso

    • (!) 16534 Comment , yoichi.aso

SR2

  • 16509 Lowering the pre-isolator , fabian.arellano

This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.

Summary Report

TypeA

TypeB

Type-Bp

PR2

As people may remember we had to move the SD keystone very high in order to have the mirror at the appropriate height:

  • At such position the TF had a smaller amplitude. See klog.
  • At the LVDT card we checked the return signal from the LVDT and it was clipping due to saturation. See example in klog.
  • We reduced the gain until we achieved a suitble sinusoidal signal and adjusted the phase to -180 degrees (not zero due to the height of the keystone).
  • Then we calibrated the OSEMs.
  • The responsivity is not as good as in other LVDTs becuase we require a large measuring range. The suitable position of the keystone is 5.3 mm above the zero of the LVDT, so it likely has a range of about 10 mm.
  • The transfer function shows a healthy system.
  • I still have to take note of the resistance values of the SF LVDT card channel.

PR3

  • We adjusted the pitch of the mirror
    • First we measured IM TFs and saw that the IN wasn't touching the IRM.
    • Then we measured the mirror pitch to be -1.4 mrad, not far away from the target of -3.3 mrad.
    • The back side is not accesible for the laser level so se used the front side.
      • ROC: 458 m
      • We set the laser level at the vertical midpoint of the mirror in order to minimize the systematic error introduced by the curvature.
    • Using the picomotor we moved the pitch to the target value of -3.3 mrad
  • Then we adjusted the positions of H2, H3 and V1 OSEMs.

Yet to do in PRM

  • We need to measure IM TFs
  • We realized we might have mistake in setting the height. We need to double check.
  • We need to double check that the H3 OSEM screws are tightened enough.
  • We require one more day.

TypeC

Electronics

Control

Safety

Discussion

Travel Plans

The week from 5/17

  • Takahashi: 5/17-21
  • Sato: 5/17-21
  • Hirata: 5/17-21
  • Yano: 5/17-21
  • Aso: 5/17-20

The week from 5/24

  • Takahashi: 5/24-28
  • Sato: 5/24-28
  • Hirata: 5/24-28
  • Yano: 5/24-28

Next meeting

  • 2021/5/21(FRI)

KAGRA/Subgroups/VIS/VISMinutes20210514 (last edited 2021-05-14 14:38:54 by RyutaroTakahashi)