= Agenda/Minutes =
[[https://zoom.us/j/203743987|Zoom Meeting]]

----------
= CRY+VIS Interface Meeting =
Date: 2021/5/14 13:00-13:55

Participants: Takahashi, Miyo, Node, Aso, Ushiba, Sato, Tomaru, Hirata, Ikeda, Kimura

[[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Upgrades/PostO3Upgrades|Post O3 Upgrade portal]]

== Schedule ==
 * IX: IP was released on 5/10. Adjustment of Yaw FR is scheduled on 5/17.
 * IY: Remedy of the pre-isolator is postponed.
 * EX: Height adjustment was finished ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16535|Status]]).
 * EY: Installation of the tower was restarted on 5/11. The maraging rod was removed. Items (pure water maker, etc.) for the mirror cleaning are under preparation.

== Status ==
 * Corrugate tube fixing jig: Other 3 sets will be ready by the end of June.
 * TM height setting: Final setting of height in EX was on 5/13. Angle adjustment in EX was scheduled on 5/13.
 * Commissioning in air: Started on the pre-isolator in IX.
 * Commissioning in vacuum:
 * Overall commissioning: Operators are necessary.
 * Acceptance check: Group work is set every Friday to make the acceptance check document.
 * PF actuator: After SC.
 * Jig for FC painting: Test is scheduled in the week of 5/17. Minimum target is to learn the procedure with the jig.

== Discussion ==
----------
= VIS Meeting =
14:00-14:40

Participants: Takahashi, Hirata, Miyo, Sato, Sugiyama, Fabian, Ishizaki, Tanaka, Aso

== Schedule ==
See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/Schedule|Schedule]]

 * Type-A team: IXV 5/17, EYV 5/18-21
 * Type-B team: FC painting test 5/17-19, MSB?

'''Milestone'''

 * ''IMC suspensions are ready in air [40]'' will finish 2011/04/21.
 * ''PRs are ready in air [643]'' will finish 2011/07/09.
 * ''ETMX is ready in air [656]'' will finish 2021/08/25.
 * ''ITMX is ready in air [657]'' will finish 2021/08/31.
 * ''ETMY is ready in air [658]'' will finish 2021/09/16.
 * ''ITMY is ready in air [659]'' will finish 2021/11/08.
 * ''BS is ready in air [691]'' will finish 2011/11/24.
 * ''SRs are ready in air [663]'' will finish 2011/12/20.
 * ''Output suspensions are ready in air [695]'' will finish 2011/12/21.
 * ''TMSY is ready in air [708]'' will finish 2011/??/??.
 * ''TMSX is ready in air [684]'' will finish 2011/??/??.

2021/03/29 updated

== Klog ==
'''EX'''

 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16535|16535]] Height adjustment of ETMX , __ryutaro.takahashi__

'''General'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16506|16506]] Deleted unnecessary processes from VIS model file. ,  __satoru.ikeda__

'''IX'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16421|16421]] Height adjustment of ITMX ,  __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16499|16499]] Comment ,  __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16519|16519]] Comment ,  __ryutaro.takahashi__

'''MCE'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16512|16512]] MCe oplev characterization ,  __takaaki.yokozawa__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16525|16525]] Comment ,  __takaaki.yokozawa__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16522|16522]] Comment , __tomotada.akutsu__

'''MCF'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16498|16498]] Type-C simulation model ,  __yoichi.aso__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16501|16501]] Oplev calibration MCo ,  __takaaki.yokozawa__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16500|16500]] Characterization of optical lever MCi ,  __takaaki.yokozawa__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16537|16537]] MCo suspension strange , __tomotada.akutsu__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16157|16157]] Investigation of IMC suspensions ,  __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16513|16513]] Comment ,  __kouseki.miyo__

'''PR3'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16520|16520]] Thermistor installation ,  __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16521|16521]] Setting the mirror to nominal height ,  __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16348|16348]] Tightening the locating clamps for the piano wire. ,  __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16502|16502]] Comment ,  __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16520|16520]] Thermistor installation ,  __fabian.arellano__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16533|16533]] Comment , __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16521|16521]] Setting the mirror to nominal height ,  __fabian.arellano__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16532|16532]] Comment , __shinji.miyoki__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16529|16529]] Comment , __fabian.arellano__

'''PRM'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16518|16518]] PRM BF-LVDT replacement ,  __yoichi.aso__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16534|16534]] Comment , __yoichi.aso__

'''SR2'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16509|16509]] Lowering the pre-isolator ,  __fabian.arellano__

This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.

== Summary Report ==
=== TypeA ===
=== TypeB ===
=== Type-Bp ===
==== PR2 ====
As people may remember we had to move the SD keystone very high in order to have the mirror at the appropriate height:

 * At such position the TF had a smaller amplitude. See klog.
 * At the LVDT card we checked the return signal from the LVDT  and it was clipping due to saturation. See example in klog.
 * We  reduced the gain until we achieved a suitble sinusoidal signal and  adjusted the phase to -180 degrees (not zero due to the height of the  keystone).
 * Then we calibrated the OSEMs.
 * The  responsivity is not as good as in other LVDTs becuase we require a  large measuring range. The suitable position of the keystone is 5.3 mm  above the zero of the LVDT, so it likely has a range of about 10 mm.
 * The transfer function shows a healthy system.
 * I still have to take note of the resistance values of the SF LVDT card channel.

==== PR3 ====
 * We adjusted the pitch of the mirror
  * First we measured IM TFs and saw that the IN wasn't touching the IRM.
  * Then we measured the mirror pitch to be -1.4 mrad, not far away from the target of -3.3 mrad.
  * The back side is not accesible for the laser level so se used the front side.
   * ROC: 458 m
   * We  set the laser level at the vertical midpoint of the mirror in order to  minimize the systematic error introduced by the curvature.
  * Using the picomotor we moved the pitch to the target value of -3.3 mrad
 * Then we adjusted the positions of H2, H3 and V1 OSEMs.

Yet to do in PRM

 * We need to measure IM TFs
 * We realized we might have mistake in setting the height. We need to double check.
 * We need to double check that the H3 OSEM screws are tightened enough.
 * We require one more day.

=== TypeC ===
=== Electronics ===
=== Control ===
== Safety ==
== Discussion ==
== Travel Plans ==
The week from 5/17

 * Takahashi: 5/17-21
 * Sato: 5/17-21
 * Hirata: 5/17-21
 * Yano: 5/17-21
 * Aso: 5/17-20

The week from 5/24

 * Takahashi: 5/24-28
 * Sato: 5/24-28
 * Hirata: 5/24-28
 * Yano: 5/24-28

== Next meeting ==
 * 2021/5/21(FRI)