Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/7/2 13:00-
Participants:
Schedule
- IX: Broken cables of TF/BF actuator were repaired.
- IY: The ballasts on the cryo-payload and the BF were adjusted. Additional spring was implemented on the BF.
- EX: Alignment for the green beam is planed in the next week.
- EY: Mirror cleaning in Mitaka is on going.
Status
- Corrugate tube fixing jig: Implementation is scheduled on 7/12-13.
- TM height setting: Next target is ITMY.
- Commissioning in air: X-arm.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check: Group work is set every Friday.
- PF actuator: After SC.
- Jig for FC painting:
- Separation of rack in 2F: On the maintenance days in July.
- Disassembly of PRM/PR2 assembly frame: It was carried out on 6/28.
- New vacuum pumps for V-chambers: Check the port location and interference of cabling.
- Extension of cables for picomotor drivers: Test is planed in EYV.
Discussion
VIS Meeting
14:00-
Participants:
Klog
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Adjustment of IYV
- Type-B team: MSB
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
Discussion
Travel Plans
The week from 7/5
- Takahashi: 7/5-8 (KIW8 7/7-9)
- Sato: 7/5-8
- Hirata: 7/5-9
- Yano: 7/5-9
The week from 7/12
- Takahashi: 7/12-16
- Sato: 7/12-16
- Hirata: 7/12-16
- Yano: 7/12-16
Next meeting
- 2021/7/16(FRI)