Date: 2021/7/9 13:00-

Participants:

Post O3 Upgrade portal

Schedule

  • IX: To the finalization.
  • EX: Alignment for the green beam was finished. To the finalization
  • IY: Height adjustment is on going.
  • EY: Mirror cleaning is on going in Mitaka.

Status

  • Corrugate tube fixing jig: Implementation is scheduled on 7/12-13.
  • TM height setting: ITMY.
  • Commissioning in air: X-arm.
  • Commissioning in vacuum:
  • Overall commissioning:
  • Acceptance check: Every Friday.
  • PF actuator: After SC.
  • Separation of rack in 2F: This is scheduled on 7/16.
  • New vacuum pumps for V-chambers: Considering the port location.
  • Extension of cables for picomotor drivers: Tested in EYV.

Discussion

Next meeting

  • 2021/7/16(FRI)